FREE BOOKS

Author's List




PREV.   NEXT  
|<   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38  
39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   >>   >|  
the caisson as soon as a foundation could be secured on sound rock. The latter was found at a depth of 38 ft. below mean high water. With the cutting edge seated at that depth, the top of the caisson was only 2 ft. above mean high water, and as this was insufficient protection against high tides, a 10-ft. extension was ordered for the top. Work, however, went on without delay on the remainder of the excavation. The junction between the cutting edge and the rock was sealed with concrete and grout. The caisson was lowered at an average rate of 0.53 ft. per day. The size of the shaft below the cutting edge was 62 ft. 7 in. by 32 ft. The average rate of excavation during the sinking in soft material was 84 cu. yd. per day. The average rate of rock excavation below the final position of the cutting edge was 125 cu. yd. per day. There were night and day shifts, each working 10 hours. Excavation in earth cost $3.96 per cu. yd., of which $1.45 was for labor and $2.51 for top charges, etc. The excavation of rock cost $8.93 per cu. yd., $2.83 being for labor and $6.10 for top charges. The final elevations of the four corners of the cutting edge, together with their displacement from the desired positions, are shown in Table 1. RIVER TUNNELS. The four river tunnels, between the Manhattan and Long Island City shafts, a distance of about 3,900 ft., were constructed by the shield method. Eight shields were erected, one on each line in each shaft, the four from Manhattan working eastward to a junction near the middle of the river with the four working westward from Long Island City. Toward the end of the work it was evident that the shields in Tunnels _B_, _C_, and _D_ would meet in the soft material a short distance east of the Blackwell's Island Reef if work were continued in all headings. In order that the junction might be made in firm material, work from Manhattan in those three tunnels was suspended when the shields reached the edge of the ledge. The shields in Tunnel _A_ met at a corresponding point without the suspension of work in either. An average of 1,760 ft. of tunnel was driven from Manhattan and 2,142 ft. from Long Island City. [Illustration: PLATE LXV, FIG. 1.--SHIELD FITTED WITH SECTIONAL SLIDING HOODS AND SLIDING EXTENSIONS TO THE FLOORS.] [Illustration: PLATE LXV, FIG. 2.--SHIELD FITTED WITH FIXED HOODS AND FIXED EXTENSIONS TO THE FLOORS.] TUNNELS DRIVEN EASTWARD FROM MANHATTAN. _Materials and In
PREV.   NEXT  
|<   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38  
39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   >>   >|  



Top keywords:
cutting
 

Manhattan

 

excavation

 

Island

 

average

 

shields

 
junction
 

caisson

 

material

 

working


tunnels

 

TUNNELS

 

EXTENSIONS

 

SLIDING

 
FLOORS
 

distance

 

Illustration

 

SHIELD

 

charges

 

FITTED


eastward
 

erected

 

Blackwell

 
evident
 
westward
 

middle

 

Toward

 

Tunnels

 

suspension

 

tunnel


driven

 

MANHATTAN

 

Materials

 

EASTWARD

 

DRIVEN

 

SECTIONAL

 

Tunnel

 
headings
 

continued

 

reached


suspended

 

remainder

 
sealed
 
concrete
 

ordered

 

lowered

 
extension
 

secured

 
foundation
 

insufficient