FREE BOOKS

Author's List




PREV.   NEXT  
|<   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44  
45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   >>   >|  
cavation was completed. METHODS OF EXCAVATION. The distribution of materials to be excavated, as previously outlined, divided the excavation into three distinct classes, for which different methods had to be developed. These three classes were: _First._--All-rock section. _Second._--Rock in the bottom, earth in the top. _Third._--All-earth section. The extent of the second and third classes was much greater than that of the first, and they, of course, determined the use of the shield. Shields had not previously been used extensively in rock work, either where the face was wholly or partly in rock, and it was necessary to develop the methods by experience. The specifications required that where rock was present in the bottom, a bed of concrete should be laid in the form of a cradle on which to advance the shield. _All Rock._--At different times, three general methods were used for excavating in all-rock sections. They may be called: The bottom-heading method; the full-face method; and the center-heading method. The bottom-heading method was first tried. A heading, about 8 ft. high and 12 ft. wide, was driven on the center line, with its bottom as nearly as possible on the grade line of the bottom of the tunnel. It was drilled in the ordinary manner by four drills mounted on two columns. The face of the headings varied from 10 to 30 ft. in advance of the cutting edge. After driving the heading for about 10 ft., the bottom was cleared out and a concrete cradle was set. The width of the cradles varied, but was generally from 8 to 10 ft. The excavation was enlarged to full size as the shield advanced, the drills being mounted in the forward compartments of the shield, as shown by Fig. 1, Plate LXVII, which represents the conditions after the opening had been cut in the bulkhead, but before the new methods, mentioned later, had been developed. [Illustration: PLATE LXVIII] The sides and top were shot downward into the heading. The area of the face remaining behind the heading was large, and a great number of holes and several rounds were required to fire the face to advantage. As soon as firing was started at the face, the heading was completely blocked, and operations there had to be suspended until the mucking was nearly completed. The bottom-heading method was probably as good as any that could be devised for use with the shields as originally installed. All the muck had to be taken from the face b
PREV.   NEXT  
|<   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44  
45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   >>   >|  



Top keywords:
heading
 

bottom

 

method

 

methods

 

shield

 

classes

 
drills
 

required

 

mounted

 

varied


center

 

advance

 

concrete

 

cradle

 
excavation
 

previously

 

section

 

developed

 

completed

 

conditions


represents
 

compartments

 

forward

 
installed
 
cleared
 

driving

 

cradles

 

shields

 

advanced

 

originally


generally

 

enlarged

 

devised

 

bulkhead

 

rounds

 

number

 

suspended

 
operations
 

firing

 

completely


advantage

 

blocked

 
mucking
 
mentioned
 

started

 

Illustration

 
downward
 

remaining

 
LXVIII
 

opening