Rock | 46 | 116 | 2.52 | |
| | | | |
Rock | 59 | 137 | 2.32 | |
| | | | |
Mixed | 25 | 48 | 1.92 | |
--------------+------+--------+--------+--------------------------------------+
LINE B, MANHATTAN.
--------------+-----------------+-------------------+-------------------------+
| | Station: | Date: |
| |---------+---------+------------+------------+
| | | | | |
Material. | Method. | From | To | From | To |
--------------+-----------------+---------+---------+------------+------------+
{|Top heading |108+35 |107+87 |July 6, '05|July 27, '05|
{|Top lift of bench|108+35 |107+87 |Aug. 3, '05|Aug. 14, '05|
Rock {|Bottom lift of | | | | |
{| bench |108+35 |108+15 |Aug. 26, '05|Aug. 30, '05|
{|Bottom lift of | | | | |
{| bench |108+15 |107+87 |Sept 11, '05|Sept 26, '05|
| | | | | |
Rock |Bottom heading |107+87 |107+00 |Oct. 23, '05|Jan. 17, '06|
| | | | | |
Mixed |Bottom heading |107+00 |106+64 |Jan. 17, '06|Feb. 12, '06|
| | | | | |
Mixed |Rock bench |106+64 |106+31 |Feb. 12, '06|Mar. 1, '06|
| | | | | |
Earth |Poling and |106+31 |105+58 |Mar. 1, '06|Apr. 3, '06|
| breasting | | | | |
| | | | | |
|Shutters in | | | | |
Earth | contact with |105+58 | 99+19 |Apr. 9, '06|Nov
|