FREE BOOKS

Author's List




PREV.   NEXT  
|<   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69  
70   71   72   73   74   75   76   77   78   >>  
n intermission of about 1/2 hour in low pressure for lunch. _Air Pressures Required._--During the greater portion of the work in soft ground, pressure was maintained which would about balance the hydrostatic head at the axis of the tunnel. This required a pressure varying from 30 to 34 lb. per sq. in. above that of the atmosphere. In Tunnels _B_ and _D_, at Manhattan, during the work in soft ground, pressures as high as 37 lb. were maintained for considerable periods of time; in the firm material near the reef 28 lb. was often sufficient. While removing the broken plates, the pressure was raised for a short time to 42 lb., and was maintained between 37-1/2 and 40 lb. for a little more than one month. _Air Supply._--For regular operation the contractor furnished four compressors on each side of the river, each having a rated capacity of 5,000 cu. ft. of free air per minute delivered at 50 lb. above normal, when running at the rate of 100 rev. per min. An additional compressor of the same capacity was supplied on each side of the river, in compliance with the requirement for 25% excess capacity; the additional compressors had also high-pressure air cylinders which could be connected at will, and in which the pressure could be increased to 150 lb., and the air used to supply rock drills, grouting machines, etc. The entire combination on each side of the river, therefore, was rated at 25,000 cu. ft. of free air per minute, or a mean of 6,250 cu. ft. per heading. Its safe working capacity was not far from 20,000 cu. ft. per min. The shields broke through rock surface in Tunnels _B_, _C_, and _D_, at Manhattan, in November and December, 1905. The consumption of air in the four tunnels soon exceeded 15,000 cu. ft. for 24 hours, and in Tunnel _D_, on several occasions, it exceeded 7,000 cu. ft. for a like period. Blows had become frequent, and it was evident that the air plant was inadequate for driving four tunnels at once in the open material east of the Manhattan rock. Work in Tunnel _A_, therefore, was not resumed, after the suspension on December 29th, for about ten months, and Tunnel _C_ was also closed down for more than four months of the time between December, 1905, and July, 1906. During this period the capacity of the plant was increased from the rated 25,000 cu. ft. of free air per minute, to 35,000. In Tunnel _D_ the material had gradually become firmer, with more clay and less escape of air, as the Blackwell
PREV.   NEXT  
|<   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69  
70   71   72   73   74   75   76   77   78   >>  



Top keywords:
pressure
 

capacity

 

Tunnel

 

material

 

Manhattan

 

December

 
minute
 

maintained

 

ground

 

additional


compressors

 

period

 

months

 

Tunnels

 
exceeded
 

During

 

tunnels

 

increased

 

intermission

 

November


surface
 

entire

 

combination

 
machines
 
drills
 

grouting

 

working

 

heading

 

shields

 

closed


resumed

 

suspension

 

escape

 

Blackwell

 

firmer

 

gradually

 

occasions

 
driving
 

inadequate

 

frequent


evident

 

consumption

 
sufficient
 
removing
 

broken

 

plates

 
raised
 

atmosphere

 
tunnel
 

required