FREE BOOKS

Author's List




PREV.   NEXT  
|<   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32  
33   34   35   36   37   38   >>  
locomotive cranes, which handled the spoil in places where timbering interfered with the operation of the shovels. All tracks were of 3-ft. gauge throughout and laid with 40-lb. rails. Practically all the heavy drilling was done with Ingersoll drills (Model E 52), the trimming being largely done with jap and baby drills. A large number of pumps were used at various points on the work, and practically all were of Cameron make, the largest ones at the shaft being 10 by 5 by 13-in. The grout machines were of the vertical-cylinder, air-stirring type. SHAFT SINKING. The sinking of the Intermediate Shafts was the first work undertaken by the contractor. The 33d Street Shaft was 34.5 ft. long, 21 ft. wide, and 83 ft. deep. The rock surface averaged 5 ft. below the ground surface. Sinking was started on July 10th, 1905, and was completed on October 3d, 1905, the rock being hard and dry. The average daily rate was 0.73 ft. and an average of 17.1 cu. yd. were excavated per day, with two shifts of 8 hr. each. The first shift started at 6 A. M. and the second at 2.30 P. M., ending at 11 P. M. These hours were adopted in order to avoid undue disturbance during the night. [Illustration: PLATE LIX, FIG. 1.--AIR-OPERATED STEAM SHOVEL USED IN TUNNEL.] [Illustration: PLATE LIX, FIG. 2.--TIMBERING IN TOP HEADINGS ABOVE I-BEAMS.] [Illustration: PLATE LIX, FIG. 3.--FIRST SECTION OF CONCRETE LINING AT FIFTH AVENUE.] [Illustration: PLATE LIX, FIG. 4.--TIMBERING AND RUBBLE MASONRY OVER I-BEAMS.] Before blasting the first lift of rock, channel cuts 5 or 6 ft. deep were made along the sides of the shaft, in order to avoid damage to the walls of neighboring buildings. Timbering was required for a depth of only 10 ft. below the surface of the ground. A drift, 30.6 ft. long, 17 ft. wide, and 27 ft. high, connected the south end of the shaft with the tunnels. The drift was excavated in three stages, a top heading and a bench in two lifts. While blasting the cut in the top heading, there was enough concussion to break glass in the neighboring buildings. The use of a radialax machine reduced the concussion somewhat, but it was very quickly abandoned on account of the length of time required for the drilling. The construction of the 32d Street Shaft was quite similar to the one on 33d Street. It was 31.5 ft. long, 20.5 ft. wide, and 71 ft. deep. The depth of earth excavation averaged 19.5 ft. The rock in this shaft was seam
PREV.   NEXT  
|<   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32  
33   34   35   36   37   38   >>  



Top keywords:
Illustration
 

Street

 

surface

 

started

 

average

 

averaged

 
ground
 

required

 

buildings

 

neighboring


concussion

 

heading

 

blasting

 

excavated

 
TIMBERING
 

drilling

 

drills

 

damage

 

HEADINGS

 

operation


handled
 

places

 

interfered

 
Timbering
 
timbering
 

channel

 

LINING

 

CONCRETE

 

SECTION

 

AVENUE


shovels

 

Before

 

RUBBLE

 

MASONRY

 

tracks

 

connected

 

construction

 
length
 

account

 

quickly


abandoned

 

similar

 
excavation
 
cranes
 

stages

 

tunnels

 
radialax
 

machine

 
reduced
 

locomotive