FREE BOOKS

Author's List




PREV.   NEXT  
|<   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  
the full width of the tunnel and advancing the face of the pit in several lifts, the muck being blown over the slope and loaded into buckets at its foot. The work was attacked at several places simultaneously, and the spoil was hoisted by derricks located at convenient points along the side of the cut. _Thirty-third Street Work in Tunnel and Open Cut._--The West 33d Street Shaft was similar to the one in 32d Street, and was sunk during February, March, and April, 1907, through 10 ft. of earth, 21 ft. of soft rock, and 29 ft. of fairly hard rock. It was necessary to timber heavily the upper 30 ft. of the shaft. The timber later showed evidences of severe strain, and had to be reinforced. [Illustration: Plate LXI.--EXCAVATION AND TIMBERING IN HEAVY GROUND OF THREE-TRACK TUNNEL OF 33D ST.] As soon as the shaft excavation was deep enough, a drift was driven part way across the tunnels, and top headings were started both east and west to explore the rock. The heading to the west was divided into two drifts, as shown on Plate LXI. These two drifts were continued to the west end of the contract, and were then enlarged to a full-sized heading and timbered, as shown on Plate LXI and Fig. 3, Plate LX. The rock near the shaft contained many wet rusty seams, and settlement was detected in the segmental tunnel timbering soon after the widening of the heading was completed. Short props were placed under the timbers, and the street surface was opened with a view of stripping the earth down to the rock and thus lightening the load on the timbering. Street traffic was maintained on a timber structure with posts eventually carried down to the rock surface, and the walls of the buildings on the north side of the street were underpinned to rock. The settlement of the tunnel timbering was checked for a time, and the bench was excavated as shown on Plate LXI. In this work the cut in the center was first made, and the short props were replaced by struts, as shown; after this the berms were removed and the side posts were placed. While building the brick arches, holes were left in the masonry around the struts. After the masonry had hardened, piers were built on the arches to support the segmental timbers. The struts were then removed and the openings filled with masonry. The voids above the arch were packed with rock and afterward thoroughly grouted. The timbers near the shaft continued to settle, and, although they had been placed
PREV.   NEXT  
|<   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:
Street
 

timbers

 

struts

 

timbering

 

heading

 

tunnel

 
masonry
 

timber

 

street

 

surface


segmental

 

drifts

 

continued

 

settlement

 
arches
 

removed

 

detected

 

building

 

completed

 

widening


support
 

openings

 

filled

 
hardened
 
contract
 

timbered

 

enlarged

 

contained

 

center

 

afterward


carried

 

structure

 

eventually

 

buildings

 

excavated

 

underpinned

 

checked

 
maintained
 

traffic

 

replaced


opened

 

settle

 
lightening
 
grouted
 

stripping

 

packed

 
Tunnel
 

Thirty

 
similar
 

February