FREE BOOKS

Author's List




PREV.   NEXT  
|<   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  
ith 3-in. plank tops, were laid on it to form the ditch and the shoulders for the flagstone covers. The track, which had previously been blocked up on the rock between the ditches, was raised and supported on the ditch boxes above the finished floor level. At the same time, light forms were braced from the ditch boxes to the grade of the base of the low-tension and telephone-duct bank. After depositing the concrete to this level, the telephone ducts were laid. The forms for the water-proofing or sand-wall up to the 15 deg. line and for the main side-walls and core-walls were built in 30-ft. panels and were supported on carriages, which, traveling on a broad-gauge track above the ditches, moved along the tunnel, section by section, as the work advanced. The panels were hung loosely from joists carrying a platform on the top chord of the carriage trusses, and were adjusted transversely by bracing and wedging them out from the carriage. The small forms for the refuge niches, ladders, etc., were collapsible, and were spiked to the main panel forms just previous to the deposition of the concrete. The concrete was deposited from the platform on top of the carriage, to which the cars were elevated in various ways. Plate LXI shows the details of the carriages, and is self-explanatory. The concrete for the sand-walls and the core-wall, to the level of the sidewalk, was deposited at the same time; two carriages in each tunnel, placed opposite each other, forming a 60-ft. length, were used at each setting. The floor section of the 4-in. tile drains had been laid with the floor concrete, and, as the sand-wall concrete was deposited, the drains were brought up simultaneously, broken stone being deposited between the tile and the rock to form a blind drain and afford access to the open joints of the tile for the water entering the tunnel through seams in the rock. The drains were spaced at intervals not exceeding 25 ft., depending on the wetness of the rock, and were placed at similar intervals in the core-wall under the lowest projecting points of the rock on the center line between the tunnels. A small ditch lined with loose 6-in. vitrified half pipe was provided in the top of the sand-wall to collect the water from the extrados of the arch and lead it to the top of the drains. Great difficulty was experienced in maintaining these drains clear, and, on completion of the work, a large amount of labor was expended in removing obst
PREV.   NEXT  
|<   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:
concrete
 

drains

 

deposited

 

carriages

 

carriage

 

section

 
tunnel
 

ditches

 

panels

 

supported


intervals

 

platform

 

telephone

 

afford

 
access
 

opposite

 

sidewalk

 

entering

 

joints

 

expended


length
 

brought

 

removing

 
simultaneously
 
forming
 

broken

 

setting

 

vitrified

 

provided

 

collect


difficulty

 

amount

 

extrados

 

tunnels

 

explanatory

 

experienced

 

depending

 
wetness
 

exceeding

 

spaced


similar

 

points

 
center
 
projecting
 

maintaining

 

lowest

 
completion
 

adjusted

 
depositing
 

tension