FREE BOOKS

Author's List




PREV.   NEXT  
|<   28   29   30   31   32   33   34   35   36   37   38   >>  
and the U. S. Water-proofing Company's compound--have been made with apparent success up to the present time, and the results after the lapse of a considerable period are awaited with interest. _Duct Laying._--The position of the electric conduits, buried in the heart of the concrete walls, interfered greatly with the economical and speedy placing of the lining, and their laying proved to be one of the most troublesome features of the work. The power conduits were single-way, with the bank for high-tension cables separated in the side-walls from the low-tension bank, as shown on Plate XII. The conduits for telephone and telegraph service were four-way, and were located in the core-wall. All ducts had 3/4-in. walls and a minimum clear opening of 3-3/8 in. square, with corners rounded. They were laid with joints broken in all directions, and in about 1/4-in. beds of 1:2-1/2 mortar. Flat steel bond-irons, 2 by 1/8 in., with split and bent ends, were placed in the joints at intervals of 3 ft. and projected into the concrete 3 in. on each side, tying together the concrete on opposite sides of the ducts. The joints were wrapped with a 6-in. strip of 10-oz. duck saturated with neat-cement grout, and, in addition, the power conduits were completely covered with a 1/2-in. coat of mortar to prevent the intrusion of cement and sand from the fluid concrete. The four-way conduits were plastered only over the wraps. Splicing chambers were provided at intervals of 400 ft. [Illustration: PLATE LXII, FIG. 1.--WATER-PROOFING OVER BRICK ARCHES.] [Illustration: PLATE LXII, FIG. 2.--TRESTLE USED IN CONCRETING IN THREE-TRACK TUNNEL.] [Illustration: PLATE LXII, FIG. 3.--METHOD OF STREET SUPPORT OVER OPEN-CUT EXCAVATION.] [Illustration: PLATE LXII, FIG. 4.--JUNCTION OF TWIN AND THREE-TRACK TUNNELS.] THREE-TRACK TUNNEL LINING. In the Three-Track Tunnels, a heavy brick arch was used for those portions constructed in tunnel, while, in the open-cut sections, the roof was of concrete. Both were completely water-proofed on the roof and sides, and in the tunnel sections the space above the brick roof was filled with rock packing. On account of the unstable nature of the rock encountered throughout, the voids in the packing were afterward filled with grout. By reference to the cross-sections, Plate XII, it will be seen that the haunches of the arch were tied together by steel I-beams anchored in the concrete, with the object of ma
PREV.   NEXT  
|<   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:
concrete
 

conduits

 

Illustration

 

joints

 

sections

 

tension

 
packing
 

TUNNEL

 

completely

 

cement


intervals

 

filled

 

mortar

 

tunnel

 
Splicing
 

chambers

 

provided

 

plastered

 

METHOD

 

covered


CONCRETING
 

ARCHES

 

prevent

 
intrusion
 
TRESTLE
 

PROOFING

 

afterward

 

reference

 

encountered

 

nature


account

 

unstable

 

anchored

 

object

 

haunches

 

proofed

 

TUNNELS

 
LINING
 

addition

 

JUNCTION


SUPPORT

 

EXCAVATION

 
Tunnels
 
constructed
 

portions

 

STREET

 
interfered
 

greatly

 
economical
 

speedy