FREE BOOKS

Author's List




PREV.   NEXT  
|<   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35  
36   37   38   >>  
General Viele's map of Manhattan Island (Plate IX[D]), with the points where difficulties in the construction of the tunnels were encountered has been noted in a previous paper. In all cases where the course of this ancient stream was crossed (except at its final intersection of 33d Street), the rock was found to be very soft and disintegrated, a large quantity of water was encountered, and heavy timbering was required. The construction at these localities will be taken up later. In addition, disintegrated rock, but of a less troublesome character, was invariably met under the depressions in the rock surface developed by the borings from the streets and test holes from the tunnels. Many of these places required timbering, and no timbering was elsewhere necessary except at the portals. These coincident conditions were especially marked in 32d Street, which for a long distance closely adjoins the course of the former creek. _Disposal of Spoil._--The materials excavated from the tunnels were dumped at the 35th Street pier on barges furnished by the Railroad Company under another contract, and were towed to points near the Bayonne peninsula where the spoil was used principally in the construction of the Greenville Freight Yards and the line across the Hackensack Meadows to the tunnels. Details of this work will be given in a subsequent paper. After December, 1907, when the excavation was about 85% completed, the contractor furnished the barges and effected the complete disposal of the spoil. _Difficulties of Excavation._--As stated in a previous paper, the excavation of the Twin Tunnel in 33d Street was continued westward to the west line of Fifth Avenue on the original grade. At that point the contractor started three drifts in the three-track section. The relation of the drifts to each other and to the cross-section are shown by Fig. 3. The center heading was driven a little in advance of those on the sides. At a distance of 65 ft. west of Fifth Avenue the rock surface was broken through in the top of the heading, and a very fine sand was encountered. For some distance east of this point the rock was badly disintegrated, and the heading required timbering. Through the soft material, tight lagging was placed on the sides and roof of the heading, and the face was protected by breast boards. There was a moderate flow of water through the cracks, and, in spite of every effort, some of the fine sand was constantly carri
PREV.   NEXT  
|<   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35  
36   37   38   >>  



Top keywords:
tunnels
 

heading

 

timbering

 

Street

 

required

 

construction

 
disintegrated
 

encountered

 

distance

 

section


drifts

 

Avenue

 

surface

 

barges

 
points
 

previous

 

contractor

 

furnished

 

excavation

 

completed


Meadows
 

started

 

original

 
Difficulties
 
effected
 

complete

 

disposal

 

Details

 

December

 

subsequent


Tunnel

 

continued

 

stated

 

Excavation

 

westward

 

protected

 

breast

 
lagging
 

Through

 

material


boards

 

effort

 
constantly
 
moderate
 

cracks

 

relation

 
center
 

driven

 
broken
 

Hackensack