FREE BOOKS

Author's List




PREV.   NEXT  
|<   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30  
31   32   33   34   35   36   37   38   >>  
ce, small blacksmith shops, for sharpening drill steel and making minor repairs, were located in the tunnels near the shafts. The concrete plant in each shaft was similar in arrangement to those at First Avenue, but the storage bins had wooden walls made of 2 by 4-in. and 2 by 6-in. scantling nailed flat on each other. The contractor's office on 33d Street backed up against the 32d Street shaft site, and the basement was used as a storeroom for supplies for both shafts. After the decision to do part of the work between Sixth and Seventh Avenues in open cut, an 8-in. air main was laid in 33d Street to the West Shafts, and air was supplied from the Intermediate Shaft for work on both streets in that neighborhood. _West-Shaft Plant._--West of Sixth Avenue, between 32d and 33d Streets and adjacent to the open-cut sections, the Railroad Company obtained from the Hudson and Manhattan Railroad Company the use of a large area from which the buildings had recently been removed, and gave the use of it to the contractor. This was of great value in prosecuting the west end of the work. The two West Shafts were located in the streets and were supplied with short timber trestles similar to those at the Intermediate Shafts. One telpher was taken from each of the Intermediate Shafts to operate at each of the West Shafts. In addition, a number of stiff-leg derricks were set up along the open-cut section, and were operated by Lidgerwood or Lambert air hoisting engines, or by electric motors, as circumstances dictated. A 15-ton Bay City locomotive crane was also used along part of the open-cut work on 32d Street. Several concrete plants were installed at points along the open-cut section, and were moved from place to place, the same general arrangement being adopted as at the plants already described. No. 3 and No. 4 Ransome mixers were used, and were generally set up at about the level of the top of the arch. The sand and stone storage bins were made of scantlings spiked together, and were necessarily rather shallow on account of the proximity of the tunnels to the street surface. _Thirty-fifth Street Pier._--For the receipt and disposal of materials at the 35th Street pier, four stiff-leg derricks, operated by electric hoisting engines, were installed. Two were used in lifting the muck buckets from the wagons and dumping their contents on the scows for final disposal (Fig. 4, Plate LVIII); and the other two were fitted with
PREV.   NEXT  
|<   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30  
31   32   33   34   35   36   37   38   >>  



Top keywords:
Street
 

Shafts

 

Intermediate

 

contractor

 

streets

 

Company

 
supplied
 

installed

 

plants

 

disposal


shafts

 

electric

 

tunnels

 

concrete

 
arrangement
 

located

 

engines

 

section

 

operated

 

derricks


hoisting
 

similar

 

storage

 
Railroad
 
Avenue
 

locomotive

 

Lambert

 

motors

 

dictated

 

points


Several

 

adopted

 

circumstances

 

general

 

shallow

 

lifting

 

buckets

 
receipt
 

materials

 

wagons


dumping

 

fitted

 
contents
 
scantlings
 

mixers

 

generally

 
spiked
 

surface

 
Thirty
 

street