FREE BOOKS

Author's List




PREV.   NEXT  
|<   297   298   299   300   301   302   303   304   305   306   307   308   309   310   311   312   313   314   315   316   317   318   319   320   321  
322   323   324   325   326   327   328   329   330   331   332   333   334   335   336   337   338   339   340   341   342   343   344   345   346   >>   >|  
ours of continuous running, or such time as may be required to burn a total of 250 pounds of coal per square foot of grate. In the case of a boiler using a mechanical stoker, the duration, where practicable, should be at least 24 hours. If the stoker is of a type that permits the quantity and condition of the fuel bed at beginning and end of the test to be accurately estimated, the duration may be reduced to 10 hours, or such time as may be required to burn the above noted total of 250 pounds per square foot. In commercial tests where the service requires continuous operation night and day, with frequent shifts of firemen, the duration of the test, whether the boilers are hand fired or stoker fired, should be at least 24 hours. Likewise in commercial tests, either of a single boiler or of a plant of several boilers, which operate regularly a certain number of hours and during the balance of the day the fires are banked, the duration should not be less than 24 hours. The duration of tests to determine the maximum evaporative capacity of a boiler, without determining the efficiency, should not be less than 3 hours. 7. STARTING AND STOPPING The conditions regarding the temperature of the furnace and boiler, the quantity and quality of the live coal and ash on the grates, the water level, and the steam pressure, should be as nearly as possible the same at the end as at the beginning of the test. To secure the desired equality of conditions with hand-fired boilers, the following method should be employed: The furnace being well heated by a preliminary run, burn the fire low, and thoroughly clean it, leaving enough live coal spread evenly over the grate (say 2 to 4 inches),[64] to serve as a foundation for the new fire. Note quickly the thickness of the coal bed as nearly as it can be estimated or measured; also the water level,[65] the steam pressure, and the time, and record the latter as the starting time. Fresh coal should then be fired from that weighed for the test, the ashpit throughly cleaned, and the regular work of the test proceeded with. Before the end of the test the fire should again be burned low and cleaned in such a manner as to leave the same amount of live coal on the grate as at the start. When this condition is reached, observe quickly the water level,[65] the steam pressure, and the t
PREV.   NEXT  
|<   297   298   299   300   301   302   303   304   305   306   307   308   309   310   311   312   313   314   315   316   317   318   319   320   321  
322   323   324   325   326   327   328   329   330   331   332   333   334   335   336   337   338   339   340   341   342   343   344   345   346   >>   >|  



Top keywords:

duration

 

boiler

 

pressure

 

boilers

 
stoker
 

quickly

 

required

 

commercial

 
cleaned
 

pounds


estimated
 
furnace
 

continuous

 

conditions

 

beginning

 

square

 

quantity

 

condition

 

evenly

 

inches


heated
 

employed

 

preliminary

 

leaving

 

spread

 

starting

 
burned
 
manner
 

Before

 
proceeded

amount

 

observe

 
reached
 

regular

 

throughly

 
measured
 
thickness
 

record

 

weighed

 

ashpit


method

 

foundation

 

temperature

 
Likewise
 

firemen

 
shifts
 

frequent

 

single

 

operate

 
regularly