FREE BOOKS

Author's List




PREV.   NEXT  
|<   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56  
57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   >>   >|  
The rubble masonry foundation is 45 feet square and rests on a 2-foot course of concrete. The subway passes under its east side within 3 feet of its center, thus cutting out about three-tenths of the original support. At this place the footing was on dry sand of considerable depth, but on the other side of the monument rock rose within 3 feet of the surface. The steep slope of the rock surface toward the subway necessitated particular care in underpinning the footings. The work was done by first driving a tunnel 6 feet wide and 7 feet high under the monument just outside the wall line of the subway. The tunnel was given a 2-foot bottom of concrete as a support for a row of wood posts a foot square, which were put in every 5 feet to carry the footing above. When these posts were securely wedged in place the tunnel was filled with rubble masonry. This wall was strong enough to carry the weight of the portion of the monument over the subway, but the monument had to be supported to prevent its breaking off when undermined. To support it thus a small tunnel was driven through the rubble masonry foundation just below the street level and a pair of plate girders run through it. A trestle bent was then built under each end of the girders in the finished excavation for the subway. The girders were wedged up against the top of the tunnel in the masonry and the excavation was carried out under the monument without any injury to that structure. [Illustration: THREE PIPES SUBSTITUTED FOR LARGE BRICK SEWER AT 110TH STREET AND LENOX AVENUE] [Illustration: SEWER SIPHON AT 149TH STREET AND RAILROAD AVENUE] [Illustration: CONCRETE SEWER BACK OF ELECTRIC DUCT MANHOLE--BROADWAY AND 58TH STREET] At 134th Street and Broadway a two-track structure of the steel beam type about 200 feet long was completed. Approaching it from the south, leading from Manhattan Valley Viaduct, was an open cut with retaining walls 300 feet long and from 3 to 13 feet in height. After all this work was finished (and it happened to be the first finished on the subway), it was decided to widen the road to three tracks, and a unique piece of work was successfully accomplished. The retaining walls were moved bodily on slides, by means of jacks, to a line 6-1/4 feet on each side, widening the roadbed 12-1/2 feet, without a break in either wall. The method of widening the steel-beam typical subway portion was equally novel. The west wall was moved bodily by jack
PREV.   NEXT  
|<   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56  
57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   >>   >|  



Top keywords:
subway
 

monument

 
tunnel
 
masonry
 

support

 

girders

 

finished

 

STREET

 

Illustration

 
rubble

AVENUE

 

retaining

 
wedged
 
bodily
 
footing
 

concrete

 
structure
 
square
 

portion

 

surface


foundation

 

widening

 

excavation

 

Street

 

SUBSTITUTED

 
Broadway
 
RAILROAD
 

CONCRETE

 

SIPHON

 

BROADWAY


MANHOLE
 
ELECTRIC
 

slides

 

accomplished

 
successfully
 
tracks
 

unique

 

roadbed

 

equally

 
typical

method

 

Manhattan

 

Valley

 
Viaduct
 

leading

 
completed
 

Approaching

 

happened

 

decided

 

height