FREE BOOKS

Author's List




PREV.   NEXT  
|<   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60  
61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   85   >>   >|  
S)] [Sidenote: _Concrete-lined Tunnel_] Between 33d Street and 42d Street under Park Avenue, between 116th Street and 120th Street under Broadway, between 157th Street and Fort George under Broadway and Eleventh Avenue (the second longest double-track rock tunnel in the United States, the Hoosac tunnel being the only one of greater length), and between 104th Street and Broadway under Central Park to Lenox Avenue, the road is in rock tunnel lined with concrete. From 116th Street to 120th Street the tunnel is 37-1/2 feet wide, one of the widest concrete arches in the world. On the section from Broadway and 103d Street to Lenox Avenue and 110th Street under Central Park, a two-track subway was driven through micaceous rock by taking out top headings and then two full-width benches. The work was done from two shafts and one portal. All drilling for the headings was done by an eight-hour night shift, using percussion drills. The blasting was done early in the morning and the day gang removed the spoil, which was hauled to the shafts and the portal in cars drawn by mules. A large part of the rock was crushed for concrete. The concrete floor was the first part of the lining to be put in place. Rails were laid on it for a traveler having moulds attached to its sides, against which the walls were built. A similar traveler followed with the centering for the arch roof, a length of about 50 feet being completed at one operation. [Illustration: FOUR COLUMN (TOWER) VIADUCT CONSTRUCTION] [Illustration: MANHATTAN VALLEY VIADUCT, LOOKING NORTH] [Illustration: ERECTION OF ARCH, MANHATTAN VALLEY VIADUCT] On the Park Avenue section from 34th Street to 41st Street two separate double-track tunnels were driven below a double-track electric railway tunnel, one on each side. The work was done from four shafts, one at each end of each tunnel. At first, top headings were employed at the north ends of both tunnels and at the south end of the west tunnel; at the south end of the east tunnel a bottom heading was used. Later, a bottom heading was also used at the south end of the west tunnel. The rock was very irregular and treacherous in character, and the strata inclined so as to make the danger of slips a serious one. The two headings of the west tunnel met in February and those of the east tunnel in March, 1902, and the widening of the tunnels to the full section was immediately begun. Despite the adoption of every precaution sugg
PREV.   NEXT  
|<   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60  
61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   85   >>   >|  



Top keywords:

Street

 
tunnel
 
Avenue
 

headings

 

concrete

 

Broadway

 

Illustration

 

VIADUCT

 
section
 

shafts


tunnels
 
double
 

heading

 

portal

 

bottom

 

VALLEY

 

driven

 
MANHATTAN
 

Central

 

length


traveler

 
similar
 
centering
 

separate

 

ERECTION

 

operation

 
COLUMN
 

CONSTRUCTION

 

completed

 

LOOKING


danger

 

Despite

 

inclined

 

adoption

 

widening

 

February

 

immediately

 

strata

 
character
 

precaution


employed

 

electric

 

railway

 
irregular
 
treacherous
 
widest
 

arches

 

taking

 

micaceous

 

subway