FREE BOOKS

Author's List




PREV.   NEXT  
|<   405   406   407   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429  
430   431   432   433   434   435   436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   453   454   >>   >|  
the blocks of the two upper tiers were cramped together. Alter settlement on the mound had ceased, a thick capping of mass concrete was laid all along the top of the superstructure; and, finally, a mound of concrete blocks was deposited at random on the mound in front of the sea face of the superstructure to break the force of the waves and prevent undermining. A similar wave-breaker, with blocks somewhat specially arranged, was deposited in front of the sloping concrete-block superstructure of the breakwater sheltering the Portuguese harbour of Marmagao on the west coast of India, more particularly with the object of preventing the undermining of the superstructure founded only 18 ft. below low water of spring tides, on a layer of rubble spread on the muddy sea-bottom, the settlement in this case being occasioned by the yielding of the soft clay bed. This breakwater having been commenced in 1884, subsequently to the failure at Madras, the superstructure, formed of concrete blocks weighing 28-1/2 to 37-1/2 tons was built in accordance with the design adopted for the reconstructed outer arms at Madras, with the exceptions that the separate sections were given a slope of 70 deg. instead of 76 deg. shorewards to ensure greater stability, that the superstructure was made 30 ft in width instead of 24 ft., that the top tier of blocks in each section was secured to the next tier by two dowels, each formed of a bundle of four rails, penetrating 3-1/2 ft. into each tier, so as to enable the top courses to be more correctly aligned than with tenons and mortises, and that the outer side of the continuous concrete-in-mass capping was raised about 22 ft. above low water (fig. 11). The rise of spring tides at Marmagao is 6 ft. [Illustration: FIG. 10.--Colombo North-West Breakwater with Titan Crane.] At Colombo the superstructures of both the south-west and north-west breakwaters were built on the sloping-block system in sections 5-1/2 ft. thick, and built at an angle of 68 deg. shorewards (fig. 10); and the blocks, from 16-1/2 to 31 tons in weight, were laid in bonded courses across each section, with four tiers of blocks in the south-west breakwater founded 20 ft. below low water on the rubble mound, and six tiers of blocks in the north-west breakwater, founded 30-3/4 ft below low water. Five oblong grooves, moreover, were formed in moulding the blocks, in
PREV.   NEXT  
|<   405   406   407   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429  
430   431   432   433   434   435   436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   453   454   >>   >|  



Top keywords:

blocks

 

superstructure

 
concrete
 

breakwater

 

formed

 

founded

 

Madras

 

sloping

 

rubble

 

Colombo


Marmagao

 
spring
 
deposited
 

capping

 
settlement
 

shorewards

 

section

 

undermining

 

sections

 

courses


mortises

 

correctly

 

tenons

 

aligned

 
dowels
 

secured

 
bundle
 

continuous

 

penetrating

 

enable


Breakwater

 
weight
 

bonded

 

grooves

 

moulding

 
oblong
 

system

 
breakwaters
 

Illustration

 

superstructures


raised

 

sheltering

 
Portuguese
 

harbour

 

arranged

 
specially
 

breaker

 
spread
 

preventing

 

object