FREE BOOKS

Author's List




PREV.   NEXT  
|<   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429   430   431   432  
433   434   435   436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   453   454   455   456   457   >>   >|  
ght walls, because the greater depth of water in which such composite breakwaters are built causes them to be exposed to larger waves under similar conditions. The superstructures of composite breakwaters erected by the United States for harbours on the shores of Lake Superior were formerly in some cases composed of timber cribs floated into position and sunk by filling them with rubble stone. On account of the cheapness of timber several years ago in those regions, this simple mode of construction was also economical, even though the rapid decay of the timber in the portions of the cribs where it was alternately wet and dry involved its renewal about every fifteen years on the average. Owing, however, to the fact that the price of timber has increased considerably, whilst that of Portland cement has been reduced, durable concrete superstructures are beginning to be substituted for the rapidly decaying cribwork structures. With the exception perhaps of the Alderney breakwater, which, owing to its exceptional exposure and the unparalleled depth into which it extended, had its superstructure so often breached by the sea that, owing to the cost of maintenance, the inner portion only has been kept in repair, the composite breakwater of Bilbao harbour has probably proved the most difficult to construct on account of its great exposure. The original design consisted of a wide rubble mound up to about 16-1/2 ft. below low water, a mound of large concrete blocks up to low water of equinoctial spring tides, and a solid masonry superstructure well protected at its outer toe by a projection of masonry, and raised several feet above high water, forming a quay sheltered by a promenade wall. The rise of equinoctial spring tides at the mouth of the river Nervion is 14-3/4 ft. In carrying out the work, however, the superstructure built in the summer months was for the most part destroyed by the following winter storms; and, accordingly, the superstructure was eventually constructed on a widened rubble base, so as to be sheltered to some extent by the outlying concrete-block mound already deposited, a system subsequently adopted in rebuilding the damaged portion of the North Pier at Tynemouth under shelter of the ruins of the previous work. The modified superstructure of the Bilbao breakwater was founded on the extended rubble mound at a depth of 16-1/4 ft. below
PREV.   NEXT  
|<   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429   430   431   432  
433   434   435   436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   453   454   455   456   457   >>   >|  



Top keywords:

superstructure

 

timber

 
rubble
 

concrete

 

breakwater

 

composite

 

account

 

Bilbao

 

sheltered

 

exposure


extended

 
portion
 
spring
 

equinoctial

 
masonry
 

breakwaters

 

superstructures

 

adopted

 

rebuilding

 

proved


blocks

 

harbour

 

deposited

 

subsequently

 
system
 

damaged

 
consisted
 

shelter

 

previous

 

design


construct

 
difficult
 

founded

 

modified

 

Tynemouth

 
original
 

outlying

 
eventually
 

Nervion

 

carrying


months

 

winter

 
storms
 

summer

 

projection

 
destroyed
 

extent

 
raised
 

constructed

 

promenade