FREE BOOKS

Author's List




PREV.   NEXT  
|<   403   404   405   406   407   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427  
428   429   430   431   432   433   434   435   436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   >>   >|  
ubble mound. Construction of the superstructure. Formerly, in constructing a large superstructure upon a rubble mound, it was a common practice to build a sea wall and a harbour wall several feet apart, and to fill up the intermediate,. space between them with rubble, so as economically to form a wide structure on the top of the mound, and provide an adequate width for a quay along the top. A sheltering wall was also generally erected on the sea side. This, for instance, was the system of construction adopted for the superstructures, founded at low water, of Holyhead breakwater, Portland inner breakwater, and St Catherine's, Jersey, breakwater. Alderney breakwater, the Tyne breakwaters and Colombo south-west breakwater were also commenced with a precisely similar method of construction. The system, however, possesses a Very serious defect for exposed situations, namely, that if once the sea can force a small opening through the sea wall, the scooping out of the rubble filling, and the overthrow of the thinner harbour wall are rapidly accomplished if the storm continues or recurs before repairs can be effected. Experience soon proved at Alderney and Tynemouth the unsuitability of the system for very exposed situations; and the intermediate rubble filling was replaced by solid hearting down to a certain depth. At Colombo, after the first 1326 ft. of the south-west breakwater had been built with two walls and intermediate rubble for the superstructure, as the exposure proved greater than had been anticipated, and a slight displacement of part of the sea wall, 24 ft. wide, had occurred, the rubble filling was discontinued, and the two walls were united into a solid superstructure 34 ft. in width. sloping block system. A difficulty experienced in constructing a solid superstructure on the top of a rubble mound consists in the settlement of the mound which takes place when the weight of the superstructure comes on it, in spite of the consolidation of the rubble under the action of the sea for one or two years before the erection of the superstructure on it is undertaken. When the superstructure is carried out in long stepped-forward courses, irregular settlement is particularly liable to occur, as the weight is progressively imposed in an uneven manner on the yielding rubble, in proportion to the height of the rubble base and its deficie
PREV.   NEXT  
|<   403   404   405   406   407   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427  
428   429   430   431   432   433   434   435   436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   >>   >|  



Top keywords:

rubble

 

superstructure

 
breakwater
 

system

 

filling

 

intermediate

 

Colombo

 

construction

 

Alderney

 

proved


settlement

 
weight
 
exposed
 

situations

 
harbour
 

constructing

 

occurred

 

displacement

 

anticipated

 

slight


discontinued

 

difficulty

 

experienced

 

consists

 
sloping
 

united

 
greater
 

practice

 

Formerly

 

exposure


common

 
hearting
 

liable

 

progressively

 

irregular

 
forward
 

courses

 
imposed
 

uneven

 

deficie


height

 

proportion

 
manner
 

yielding

 

stepped

 
consolidation
 

Construction

 
replaced
 

action

 

undertaken