FREE BOOKS

Author's List




PREV.   NEXT  
|<   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   260   261   262   263   264   265   266   267   268  
269   270   271   272   273   274   275   276   277   278   279   280   281   282   283   284   285   286   287   288   289   290   291   292   293   >>   >|  
a windlass placed at the other end of the barge, the pole being prevented from rising by a hitched rope which caused the "spoon" to penetrate the bottom and fill the bag. When the "spoon" reached the end of the barge where the windlass was placed, the winding was still continued, and the suspended rope being nearly perpendicular the "bag" was raised to the gunwale of the barge and the excavated material emptied into the barge. The "bag" was then hauled back to the opposite end to be lowered for another supply. This system is still in use, but is only adaptable to a limited depth of water and a soft bottom; it has been largely used in canals and frequently in the Thames. At the Fosdyke Canal in Lincolnshire 135,000 tons were raised in the manner described. According to J. J. Webster (_Proc. Inst. C. E._ vol. 89), the first application of steam power for dredging operations was to a "spoon & bag" dredger for cleansing Sunderland harbour, the engine being made by Messrs Boulton & Watt of Soho, Birmingham. _Dredging by Bucket between Two Lighters._--Another plan of dredging, practised at an early period in rivers of considerable breadth, was to moor two barges, one on each side of the river. Between them was slung an iron dredging bucket, which was attached to both barges by chains wound on the barrels of a crab winch worked by six men in one barge and round a simple windlass worked by two men in the other barge. The bucket, being lowered at the side of the barge carrying the windlass, was drawn across the bottom of the river by the crab winch on the other barge; and having been raised and emptied, it was hauled across by the opposite windlass for repetition of the process. This process was in use in the River Tay until 1833. _Bucket Ladder Dredgers._--The earliest record of a bucket ladder dredger is contained in the first paper of the first volume (1836) of the _Transactions_ of the Institution of Civil Engineers. This machine was brought into use at the Hull Docks about 1782. The bucket chain was driven by two horses working a horse-gear on the deck of the vessel. The buckets were constructed of 5/8 in. bars of iron spaced 1/8 in. apart, and were 4 ft. long, 13 in. deep, 12 in. wide at the mouth and about 6 in. wide at the bottom. This dredger raised about 30 tons per hour at the cost of 2-1/2d. per ton, which covered the wages of three men working the dredger, eight men working the lighters and the keep of three hor
PREV.   NEXT  
|<   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   260   261   262   263   264   265   266   267   268  
269   270   271   272   273   274   275   276   277   278   279   280   281   282   283   284   285   286   287   288   289   290   291   292   293   >>   >|  



Top keywords:

windlass

 

raised

 

dredger

 

bottom

 

bucket

 

working

 
dredging
 
barges
 

process

 

Bucket


worked

 

hauled

 

emptied

 

lowered

 

opposite

 

carrying

 

simple

 

Ladder

 

repetition

 
attached

lighters

 

chains

 

Dredgers

 

covered

 

barrels

 

ladder

 

driven

 

horses

 
vessel
 

buckets


spaced

 

constructed

 

volume

 

contained

 

record

 
Transactions
 

Institution

 

brought

 

machine

 

Engineers


earliest

 
adaptable
 

limited

 

system

 

supply

 

Thames

 
Fosdyke
 

frequently

 

canals

 
largely