and delivering it on the marsh at the back of the bank of the river
Thames at Crossness, Kent. A stage constructed of wooden piles
commanded a series of barge beds, and the unloading dredger running
from end to end of the stage, lifted and delivered the materials on
the marsh behind the river wall at the cost of 1 d. per cub. yd.
_Dredging on the River Scheldt below Antwerp._--This dredging took place
at Krankeloon and the Belgian Sluis under the direction of L. Van
Gansberghe. At Melsele there is a pronounced bend in the river, causing
a bar at the Pass of Port Philip, and just below the pass of Lillo there
is a cross-over in the current, making a neutral point and forming a
shoal. After dredging to 8 metres (26.24 ft.) below low tide, in clay
containing stone and ferruginous matter, a sandstone formation was
encountered, which was very compact and difficult to raise. A suction
dredger being unsuited to the work, a bucket-ladder dredger was
employed. The dredging was commenced at Krankeloon in September 1894 and
continued to the end of 1897. A depth of 6 metres (19.68 ft.) was
excavated at first, but was afterwards increased to 8 metres (26.24
ft.). The place of deposit was at first on lands acquired by the State,
2.17 m. above Krankeloon, and placed at the disposal of the contractor.
The dredgings excavated by the bucket-ladder dredger were deposited in
scows, which were towed to the front of the deposit ground and
discharged by a suction pump fixed in a special boat, moored close to
the bank of the river. The material brought by the suction dredger in
its own hull was discharged by a plant fixed upon the dredger itself. In
both instances the material was deposited at a distance of 1640 ft. from
the river, the spoil bank varying in depth from 2 to 7 metres. The water
thrown out behind the dyke with the excavated material returned to the
river, after settlement, by a special discharge lock built under the
dyke. After 1896 the material was delivered into an abandoned pass by
means of barges with bottom hopper doors or by the suction dredger. One
suction dredger and three bucket-ladder dredgers were employed upon the
work, and a vessel called "Scheldt I." used for discharging the material
from the scows. Four tugboats and twenty scows were also employed.
The largest dredger, "Scheldt III.," was 147.63 ft. long by 22.96 ft.
wide by 10.98 ft. deep, and had buckets of 21.18 cub. ft. capacity.
The output per
|