FREE BOOKS

Author's List




PREV.   NEXT  
|<   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   >>  
d by transits on shore and the elevation by measuring from the surface of the water, a tide gauge being continually observed and the time of soundings and gauge readings kept. In the river wash-borings were made from a floating pile-driver on which was installed a diamond-drill outfit of rods, pump, etc. Fourteen borings were completed in the river. Considerable difficulty was found in holding the pile-driver against the current, the material in the bottom being very soft, and several borings were lost owing to the drifting of the pile-driver. Each boring was continued, and the depth of several was more than 250 ft. below the surface of the water. The borings on land were mostly core borings, and were generally made with the chilled shot boring machine. Base lines, about 2,250 ft. in length, were measured on each side of the river, and observation points established. It was necessary to build a triangulation tower 60 ft. high on the New Jersey side as an observation point. The base lines were measured with 100-ft. steel tapes which were tested repeatedly, and the work was done at night in order to obtain the benefit of uniform temperature and freedom from traffic interruptions. From the base line on the New Jersey side, which passed over the Weehawken Shaft, an elevated point on the assumed center line on the side of Bergen Hill was triangulated to, and from this point westward a closed polygon was measured along the streets to the top of the hill on the west side and thence along the assumed center line to the portal. The level transfer across the river was made by sighting across in opposite directions simultaneously, and also by tide gauges. The outline of the final triangulation system is shown on Plate VII. [Illustration: FIG. 2.--(Full page image) HYDRAULIC SCREWING MACHINE WITH RATCHET DRIVE AND VERTICAL JACK GENERAL ARRANGEMENT] [Illustration: FIG. 3.--(Full page image) HYDRAULIC SCREWING MACHINE WITH RATCHET DRIVE AND VERTICAL JACK DETAILS] The decision as to the locations of the shafts on both sides of the river, for construction purposes and finally for permanent use, was a comparatively simple matter, and, all circumstances considered, they are unquestionably in the most suitable places. On the New York side the shaft was as near as practicable to the line dividing the subaqueous iron-lined tunnels from the land tunnels, and on the New Jersey side the shaft was placed centrally on the line
PREV.   NEXT  
|<   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   >>  



Top keywords:

borings

 

Jersey

 
driver
 
measured
 
observation
 

surface

 

Illustration

 

boring

 

center

 

triangulation


VERTICAL

 

tunnels

 

assumed

 

RATCHET

 

MACHINE

 
HYDRAULIC
 

SCREWING

 
opposite
 

streets

 
polygon

closed

 

westward

 
Bergen
 

triangulated

 

portal

 

gauges

 

outline

 

simultaneously

 

directions

 

transfer


sighting

 
system
 

ARRANGEMENT

 

suitable

 

places

 

unquestionably

 

considered

 

centrally

 

subaqueous

 

practicable


dividing

 

circumstances

 

locations

 

shafts

 

decision

 

DETAILS

 
GENERAL
 
construction
 
comparatively
 

simple