FREE BOOKS

Author's List




PREV.   NEXT  
|<   20   21   22   23   24   25   26   27   28   29   30   31   >>  
the Board. Inasmuch as the shield method of construction was required, the writer designed a shield for use in the North River Tunnels. The shield was about 18 ft. long, over all, and was provided with a rigid but removable hood extending beyond the normal line of the cutting edge, for use in sand, gravel, and ballast, to be removed when the shield reached the silt. The shields were thrust forward by twenty-four rams capable of exerting a pressure of 3,400 tons at a hydraulic pressure of 5,000 lb. per sq. in. Taking into account 30 lb. air pressure, this pressure was increased to 4,400 tons. The shield was fitted with a single hydraulic erector and hydraulic sliding platforms, and when complete weighed 194 tons. Fig. 9 is a back elevation and section of the shield. The contract for the river tunnels was let to the O'Rourke Engineering Construction Company on May 2d, 1904. The shields were built in accordance with the design previously referred to, and proved entirely satisfactory. Generally, the materials passed through were as follows: Starting out in full face rock, from it into a mixed face of rock and sand, thence into sand and gravel, full face of sand, piles, rip-rap, and the Hudson silt; and all were fully charged with water. Compressed air, at an average gauge pressure of about 25 lb. and a maximum of 40 lb. per sq. in., was used in the tunnels from the time the shields emerged from full rock face until the tunnel lining had been joined up and all caulking and grummeting had been done. [Illustration: FIG. 5.--(Full page image) ARRANGEMENT OF STRUCTURES SUPPORTING NINTH AVE. DURING PROGRESS OF EXCAVATION] Contractor's plants were established at the Weehawken Shaft and at the Manhattan Shaft, including at each, low-pressure air compressors of a capacity of 13,000 cu. ft. of free air per minute and also high-pressure air compressors for drills, hydraulic pumps, electric generators, etc. The river tunnels passed under Pier 72, North River (old No. 62), which was occupied by the New York Central and Hudson River Railroad Company. The Tunnel Company leased this pier and withdrew all the piles on the lines of the tunnels prior to the commencement of construction, and on the remaining piles constructed a trestle for the disposal of the excavation from the tunnels and the terminal. At the completion of the work this pier had to be restored, and Fig. 10 shows the general arrangements of the location of t
PREV.   NEXT  
|<   20   21   22   23   24   25   26   27   28   29   30   31   >>  



Top keywords:

pressure

 

shield

 
tunnels
 
hydraulic
 
Company
 

shields

 

passed

 

construction

 

compressors

 

Hudson


gravel

 

Contractor

 

EXCAVATION

 

PROGRESS

 

DURING

 
Weehawken
 

established

 
emerged
 

SUPPORTING

 
plants

ARRANGEMENT

 

general

 
Illustration
 

arrangements

 

joined

 

caulking

 

location

 

grummeting

 

Manhattan

 

tunnel


lining

 
STRUCTURES
 

Central

 

terminal

 

occupied

 

excavation

 

Railroad

 

commencement

 

remaining

 

withdrew


trestle

 

Tunnel

 

disposal

 

leased

 

completion

 

minute

 
constructed
 
capacity
 
drills
 

restored