FREE BOOKS

Author's List




PREV.   NEXT  
|<   19   20   21   22   23   24   25   26   27   28   29   30   31   >>  
, and a viaduct was erected to carry Ninth Avenue. The length of this viaduct is about 375 ft., and the steelwork and its erection was done apart from the North River Division work, but all excavation and underpinning was included in this division. The contract for this work on the Terminal Station-West was let to the New York Contracting Company-Pennsylvania Terminal, on April 28th, 1906, and included about 517,000 cu. yd. of excavation, about 87% being rock, the construction of about 2,000 lin. ft. of retaining and face walls containing about 18,500 cu. yd. of concrete, and a large quantity of structural steel (1,475,000 lb.) for temporary use in underpinning Ninth Avenue. Fig. 4 shows cross-sections of the Terminal Station-West yard, and Fig. 5 shows the general method of underpinning the Ninth Avenue structures. [Illustration: FIG. 4.--TERMINAL STATION WEST TYPICAL SECTIONS] _River Tunnels._--In the original plan a four-track tunnel was contemplated from the east side of Tenth Avenue to the east side of Eleventh Avenue, but, owing to the extension of the Terminal Yard, previously noted, this plan was changed, and a two-track structure was built having a central wall between the tracks. This was constructed in tunnel, with the exception of 172 ft. about midway between Tenth and Eleventh Avenues, where the rock dipped below the roof of the tunnel, and there the construction was made in open cut. These tunnels were lined with concrete with brick arches, Figs. 6, 7, and 8 being typical cross-sections. This work was executed by the O'Rourke Engineering Construction Company, under a contract dated November 1st, 1904. It was possible to excavate in full rock cover about 250 ft. of the tunnels eastward from the Weehawken Shaft and 225 ft. westward from the Manhattan Shaft. At these points the rock cover was very thin, and there shield chambers were made for the erection of two sets of shields, about 6,100 ft. apart. A typical cross-section of the Weehawken Land Tunnel is shown on Plate VIII. [Illustration: Plate VIII.--Typical Sections Between Manholes, Bergen Hill Tunnels] The Board of Engineers decided, and it was so stated in the contract and specifications, that the river tunnels should be constructed by means of hydraulic shields, but bidders were permitted to present to the Board any scheme on which they might desire to bid, but, of course, the decision as to the practicability of such plans rested with
PREV.   NEXT  
|<   19   20   21   22   23   24   25   26   27   28   29   30   31   >>  



Top keywords:

Avenue

 

Terminal

 
underpinning
 
contract
 
tunnels
 

tunnel

 

concrete

 

construction

 

Weehawken

 

sections


Illustration

 

shields

 

Tunnels

 

Eleventh

 

Company

 
included
 

Station

 
excavation
 

erection

 
constructed

viaduct

 

typical

 
executed
 

Manhattan

 

westward

 

excavate

 

November

 

points

 

Engineering

 

eastward


Construction

 
Rourke
 

present

 

scheme

 

permitted

 

bidders

 

hydraulic

 

practicability

 

rested

 

decision


desire

 

section

 

Tunnel

 

shield

 

chambers

 

Typical

 
Sections
 
stated
 
specifications
 

decided