FREE BOOKS

Author's List




PREV.   NEXT  
|<   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42  
43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  
cut down to 71-1/2 hours. The average yardage was, for the earlier period, 152 an hour, of actual excavation; and for the later period, 445 an hour--an increase of almost 200 per cent. The situation had been met. This was the period when the cost of labor and material began to jump. Employers were bidding against each other for men, and the government's work practically fixed the price of supplies. George M. Wells, consulting engineer, in his report of December 9, 1918, to the Dock Board, summarized labor increases over the scale when the work was begun, as follows: Unskilled labor, 54%; pile driver men, 40%; machinists, 40%; blacksmiths, 40%; foremen and monthly, 15 to 40%--an average increase of 40%. Materials had advanced, he went on to show, as follows: Gravel, 72%; sand, 25%; cement, 10%; lumber (form), 70%; timber, 40%; piles, untreated, 40%; piles, treated, 25%. These increases, together with the expansion of the plans requiring a canal of maximum depth, instead of the pilot cut of fifteen feet, as originally planned; the insistence of the Levee Board that levees in the back areas must be raised to elevation 30; development of unforeseen and unforeseeable quicksand conditions in the various excavations; requirements of railroads for bridges of greater capacity and strength than needed; building of a power line to the Foundation Company's plant--not a Dock Board job, but one that the conditions required it should finance then; and other expenses, besides delaying the work, made another bond issue necessary to finish the job. At its meeting of February 26, 1919, President Thompson laid the matter before the board. It decided to issue $6,000,000 of bonds, for which the same syndicate of bankers that had taken the other two offered 96. Liberty bonds were then selling at a big discount, and this seemed the best terms on which the money could be secured. This gave a total issue of $12,000,000 to date, the interest on which amounted to $600,000 a year. The Levee Board raised its share of the "rental" to $550,000, to guarantee the interest; the Public Belt Railroad's $50,000 made the total complete. In the meantime ships were beginning to bulk large on the ways of the Foundation and the Doullut & Williams yards. The Foundation company launched its first, the Gauchy--a 4,200-ton non-sinkable steel ship, built for the French government--in September, 1919; and the Doullut & Williams company launched its first, th
PREV.   NEXT  
|<   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42  
43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  



Top keywords:

period

 
Foundation
 

government

 
interest
 

increases

 

launched

 
company
 

raised

 

increase

 

Williams


conditions

 
Doullut
 

average

 

February

 

decided

 

President

 

matter

 
Thompson
 

expenses

 

required


Company

 

needed

 

building

 

finish

 

delaying

 
finance
 
meeting
 

meantime

 
beginning
 

complete


Public
 

guarantee

 

Railroad

 

French

 
September
 

sinkable

 

Gauchy

 

rental

 
selling
 

discount


Liberty

 
bankers
 

offered

 

amounted

 

secured

 
syndicate
 

levees

 
consulting
 

engineer

 

report