FREE BOOKS

Author's List




PREV.   NEXT  
|<   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59  
60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   >>   >|  
there had been any tendency to rupture. In the other cases, the concrete arches being turned between iron beams, the strength of the floor was limited by that of the beams, so the extreme load could not be put on; but the curious fact was established that a section of concrete flat on top, and forming a regular segmental arc beneath, was far stronger than one in which a portion of the under surface was parallel to the upper; showing, apparently, that the arched form, even with homogeneous concrete, causes the conversion of a large part of a vertical pressure into lateral thrust, reducing by so much the tendency of the load to break the concrete transversely. This observation is important theoretically as well as practically. It has been of late generally maintained that a concrete arch is not an arch at all, but a lintel, without thrust, and that the common form, flat above and arched beneath, is objectionable, as it gives least material at the centre, where a lintel is most strained. The Erfurt experiments directly contradict this view, and it remains for some students of architecture to render the profession a service by repeating them, and, at the same time, actually determining the thrust, for a given load, of arches of particular forms. Until this is done, the concrete construction, which is likely, we may hope, to become before many years the prevailing one in our cities, will be practised with difficulty and uncertainty, if not with danger. Incidentally, a trial was made of the effect of freezing on the concrete. The floor of a room arched in four bays, between iron beams, had just been finished when the weather became cold, and on the morning after its completion the thermometer stood at twenty above zero. The concrete had not been protected in any way, and the contractor was notified that it had been frozen, and must be removed. This was early in December, and it was about the first of April before the work of removal, preliminary to replacing the concrete with new material, was begun. Three bays had been wholly or partly removed when the hardness of the concrete under the workmen's tools attracted attention, and the arch remaining intact was tested with a load of three hundred pounds per square foot, which it bore perfectly. * * * * * The question how far an architect can be held responsible in damages, in cases where the cost of work exceeds the estimates, is examined in a
PREV.   NEXT  
|<   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59  
60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   >>   >|  



Top keywords:

concrete

 

thrust

 

arched

 

tendency

 

beneath

 

material

 

arches

 

removed

 

lintel

 

twenty


completion
 

morning

 

thermometer

 
cities
 

practised

 

difficulty

 

prevailing

 

uncertainty

 
finished
 

freezing


effect

 

danger

 
Incidentally
 

protected

 

weather

 
square
 

pounds

 

hundred

 

remaining

 

intact


tested
 

perfectly

 
question
 
exceeds
 

estimates

 

examined

 

damages

 

responsible

 

architect

 

attention


attracted
 

removal

 

December

 

contractor

 
notified
 

frozen

 

preliminary

 

replacing

 

hardness

 
workmen