preliminary labors connected with a test being satisfactorily
disposed of, it only remains to place the turbines under the required
conditions, and to then proceed with the test. For the benefit of those
inexperienced in the operation of large turbines, we will assume that
such a machine is about to be started for the purpose outlined.
It is always advisable to make a strict practice of getting all the
auxiliary plant under way before starting up the turbine. In handling a
turbine plant the several operations might be carried through in the
following order:
(1) Circulating oil through all bearings and oil chambers.[5]
(2) Starting of condenser circulating-water pumps, and continuous
circulation of circulating water through the tubes of condenser.
(3) Starting of pump delivering condensed steam from the condenser
hot-well to weighing tanks.
(4) Starting of air pump, vacuum being raised as high as possible within
condenser.
(5) Sealing of turbine glands, whether of liquid or steam type, no
adjustment of the quantity of sealing fluid being necessary, however, at
this point.
(6) Adjustment of valves on and leading to the water-weighing tanks.
(7) Opening of main exhaust valve or valves between turbine and
condenser.
(8) Starting up of turbine and slowly running to speed.
(9) Application of load, and adjustment of gland-sealing steam.
[5] In a self-contained system, where the oil pump is usually driven
from the turbine spindle, this would of course be impossible. In the
gravity and allied systems, however, it should always be the first
operation performed. The tests for oil consumption, described
previously, having been carried out, it is assumed that suitable means
have been adopted to restrict the total oil flow through the bearings to
a minimum quantity.
The running to speed of large turbo-alternators requires considerable
care, and should always be done slowly; that is to say the rate of
acceleration should be slow. It is well known that the vibration of a
heavy unit is accompanied by a synchronous or non-synchronous vibration
of the foundation upon which it rests. The nearest approach to perfect
synchronism between unit and foundation is obtained by a gradual rise in
speed. A machine run up to speed too quickly might, after passing the
critical speed, settle down with little visible vibration, but at a
later time, even hours after, suddenly begin vibrating violently from no
apparent cause. The
|