FREE BOOKS

Author's List




PREV.   NEXT  
|<   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   85  
86   87   88   89   >>  
preliminary labors connected with a test being satisfactorily disposed of, it only remains to place the turbines under the required conditions, and to then proceed with the test. For the benefit of those inexperienced in the operation of large turbines, we will assume that such a machine is about to be started for the purpose outlined. It is always advisable to make a strict practice of getting all the auxiliary plant under way before starting up the turbine. In handling a turbine plant the several operations might be carried through in the following order: (1) Circulating oil through all bearings and oil chambers.[5] (2) Starting of condenser circulating-water pumps, and continuous circulation of circulating water through the tubes of condenser. (3) Starting of pump delivering condensed steam from the condenser hot-well to weighing tanks. (4) Starting of air pump, vacuum being raised as high as possible within condenser. (5) Sealing of turbine glands, whether of liquid or steam type, no adjustment of the quantity of sealing fluid being necessary, however, at this point. (6) Adjustment of valves on and leading to the water-weighing tanks. (7) Opening of main exhaust valve or valves between turbine and condenser. (8) Starting up of turbine and slowly running to speed. (9) Application of load, and adjustment of gland-sealing steam. [5] In a self-contained system, where the oil pump is usually driven from the turbine spindle, this would of course be impossible. In the gravity and allied systems, however, it should always be the first operation performed. The tests for oil consumption, described previously, having been carried out, it is assumed that suitable means have been adopted to restrict the total oil flow through the bearings to a minimum quantity. The running to speed of large turbo-alternators requires considerable care, and should always be done slowly; that is to say the rate of acceleration should be slow. It is well known that the vibration of a heavy unit is accompanied by a synchronous or non-synchronous vibration of the foundation upon which it rests. The nearest approach to perfect synchronism between unit and foundation is obtained by a gradual rise in speed. A machine run up to speed too quickly might, after passing the critical speed, settle down with little visible vibration, but at a later time, even hours after, suddenly begin vibrating violently from no apparent cause. The
PREV.   NEXT  
|<   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   85  
86   87   88   89   >>  



Top keywords:
turbine
 

condenser

 

Starting

 
vibration
 

circulating

 

bearings

 
carried
 

sealing

 

running

 
slowly

foundation

 

synchronous

 

valves

 
adjustment
 
weighing
 

quantity

 

machine

 

turbines

 
operation
 

minimum


adopted

 

restrict

 

requires

 

acceleration

 

alternators

 

considerable

 

systems

 

allied

 

gravity

 

impossible


performed

 

remains

 
assumed
 

previously

 

consumption

 
suitable
 

satisfactorily

 

visible

 

settle

 

critical


quickly

 

preliminary

 
passing
 

violently

 

apparent

 
vibrating
 

suddenly

 
labors
 
connected
 
accompanied