FREE BOOKS

Author's List




PREV.   NEXT  
|<   79   80   81   82   83   84   85   86   87   88   89   >>  
iderable period of time in which to cool. Before any radical changes were made it was decided that a man should crawl in the suction pipe A, and remove such sand, dirt, or any other obstacles as were believed to cause the friction. After this had been done and considerable sand had been removed, tests were resumed with practically the same results as before. The investigation was continued and the dry-vacuum pumps were overhauled, as they had been damaged by water in the cylinders, and furthermore needed re-boring. In short, the auxiliaries were restored to the best condition that could be brought about by the individual improvement of each piece of apparatus. As this was not the seat of the trouble, however, the remedy failed to effect a "cure." It was demonstrated that the steam consumption of the turbines was greatly increased due to priming of the boilers, as well as condensation in the turbine casing; hence, the ills above mentioned were aggravated. Changes in Piping After a great deal of argument from the chief engineer, and the firm which furnished the pump, both making a strong plea for a change in the piping, the company accepted the inevitable, and the dotted portion shows the present layout. The elbow M was removed, and a tee put in its place to which the piping D was connected. The circulating pump was removed to the position shown, and a direct connection substituted for the S-bend. The discharge pipe C was carried from No. 1 unit separately, as shown in the elevation, and terminated at No. 1 cooling tower instead of No. 2, which shortened the distance about 60 feet, the total length of pipe (one way) from No. 1 unit being originally 250 feet. In this way the condensing equipment was made practically separate for each turbine, as it should have been in the first place. With the new piping a vacuum of 24 inches on the peak could be reached. While this is far from an efficient value, yet it is better than the former figure. The failure to reach a vacuum of 28 inches or better is due primarily to a lack of cooling water, but an improvement in this regard could be made by reconstructing the cooling towers, which at present do not offer the proper amount of cooling surface. The screens used were heavy galvanized wire of about 3/16-inch mesh, which became coated in a short time, and must be thoroughly cleaned to permit the water to drop through them. The supply of cooling water was taken from a 30-inch
PREV.   NEXT  
|<   79   80   81   82   83   84   85   86   87   88   89   >>  



Top keywords:
cooling
 

vacuum

 
piping
 

removed

 
improvement
 
present
 
inches
 

turbine

 

practically

 

iderable


elevation

 

separately

 

terminated

 

shortened

 

length

 

coated

 

distance

 

permit

 

circulating

 

position


supply

 

direct

 

connected

 

connection

 
substituted
 
carried
 

originally

 

discharge

 

cleaned

 

equipment


figure

 
failure
 
screens
 

galvanized

 

surface

 

towers

 

proper

 

reconstructing

 

regard

 
primarily

condensing
 
amount
 

separate

 

efficient

 
reached
 

strong

 

overhauled

 

damaged

 

cylinders

 
period