FREE BOOKS

Author's List




PREV.   NEXT  
|<   213   214   215   216   217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234   235   236   237  
238   239   240   241   242   243   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   260   261   262   >>   >|  
the line of the tunnel had a much greater effect than the concentration of that power at any one spot. It soon appeared that the water had found its master. Protected by the pumps, which cleared a space for the engineering operations--carried on in the midst, as it were, of two almost perpendicular walls of water and sand on either side--the workmen proceeded with the building of the tunnel at numerous points. Every exertion was used to wall in the dangerous parts as quickly as possible; the excavators and bricklayers labouring night and day until the work was finished. Even while under the protection of the immense pumping power above described, it often happened that the bricks were scarcely covered with cement ready for the setting, ere they were washed quite clean by the streams of water which poured from overhead. The men were accordingly under the necessity of holding over their work large whisks of straw and other appliances to protect the bricks and cement at the moment of setting. The quantity of water pumped out of the sand bed during eight months of incessant pumping, averaged 2,000 gallons per minute, raised from an average depth of 120 feet. It is difficult to form an adequate idea of the bulk of the water thus raised, but it may be stated that if allowed to flow for three hours only, it would fill a lake one acre square to the depth of one foot, and if allowed to flow for one entire day it would fill the lake to over eight feet in depth, or sufficient to float vessels of 100 tons burthen. The water pumped out of the tunnel while the work was in progress would be nearly equivalent to the contents of the Thames at high water, between London and Woolwich. It is a curious circumstance that notwithstanding the quantity thus removed, the level of the surface of the water in the tunnel was only lowered about 2.5 to 3 inches per week, proving the vast area of the quicksand, which probably extended along the entire ridge of land under which the railway passed. The cost of the line was greatly increased by the difficulties encountered at Kilsby. The original estimate for the tunnel was only 99,000 pounds; but before it was finished it had cost more than 100 pounds per lineal yard forward, or a total of nearly 300,000 pounds. The expenditure on the other parts of the line also greatly exceeded the amount first set down by the engineer; and before the works were finished it was more than doubled. The lan
PREV.   NEXT  
|<   213   214   215   216   217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234   235   236   237  
238   239   240   241   242   243   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   260   261   262   >>   >|  



Top keywords:

tunnel

 

pounds

 

finished

 
entire
 

quantity

 

bricks

 

pumped

 

pumping

 

greatly

 

allowed


cement
 

setting

 

raised

 
equivalent
 

contents

 

Thames

 

progress

 

stated

 

square

 

sufficient


vessels
 

burthen

 

lineal

 

forward

 

estimate

 
difficulties
 
encountered
 

Kilsby

 

original

 

expenditure


engineer
 

doubled

 

exceeded

 

amount

 

increased

 

passed

 
surface
 

lowered

 

removed

 
Woolwich

curious

 
circumstance
 

notwithstanding

 
inches
 

railway

 

extended

 

proving

 

quicksand

 

London

 

protect