FREE BOOKS

Author's List




PREV.   NEXT  
|<   200   201   202   203   204   205   206   207   208   209   210   211   212   213   214   215   216   217   218   219   220   221   222   223   224  
225   226   227   228   229   230   231   232   233   234   235   236   237   238   239   240   241   242   243   244   245   246   247   248   249   >>   >|  
r. Taylor's secretary came in and announced that the meeting had adjourned until the next day. We all left the room then. At 10 o'clock the next morning, November 11, 1904, Mr. Schmitt and myself went to Mr. Taylor's office, where I filed my bid in writing for $76,600 to cover all the buildings shown in the specifications. We waited there until about 4 o'clock, expecting some decision from the salvage committee. About 4 o'clock Mr. Taylor's secretary came in and announced that the meeting of the salvage committee had adjourned until the following Monday. The conditions embodied in the specifications as to the time allowed for removal of the wreckage were so prohibitive as to render it almost impossible to carry them out. The time limit--namely, three months--was too short. It would entail an enormous expense and waste of material to try to comply with the time conditions stated in the specifications. The amount required by the specifications to be deposited in the form of a certified check, payable to the Exposition Company, viz, 50 per cent of the amount of bid, was very exorbitant. This check was to be forfeited to the Exposition Company in the event the successful bidder failed to enter into a contract with the salvage committee within five days after they accepted the bid. I consider the amount demanded, 50 per cent, very excessive, and it had the effect of frightening bidders away. A 5 to 10 per cent deposit is usually the amount required by the Government and the city. The specifications also stipulated that the full amount of the contract, less the amount of the certified check, held and to be appropriated by the Exposition Company, must be paid to the Exposition Company at the time the contract is signed. I consider this out of all reason, and in itself would have a tendency to prohibit bidding. The time-limit clause, namely, three months, from March 1 to June 1, 1905, in which all the buildings must be torn down and the grounds cleared, was entirely too short a time, and out of all reason, as it would be physically impossible for any contractor to do the work in the time specified, and no contractor would attempt it under the terms of the specifications unless he knew he would be favored with an extension of time later on. The specifications appear to me to have been drawn up with the intent and purpose of discouraging bidders. In all my experience I have never encountered such requirements as set for
PREV.   NEXT  
|<   200   201   202   203   204   205   206   207   208   209   210   211   212   213   214   215   216   217   218   219   220   221   222   223   224  
225   226   227   228   229   230   231   232   233   234   235   236   237   238   239   240   241   242   243   244   245   246   247   248   249   >>   >|  



Top keywords:

specifications

 
amount
 

Company

 
Exposition
 
contract
 

committee

 

salvage

 

Taylor

 
months
 
impossible

bidders
 

adjourned

 

announced

 

secretary

 

certified

 

required

 

reason

 

contractor

 
meeting
 
conditions

buildings

 

appropriated

 

experience

 

purpose

 

signed

 

intent

 
discouraging
 
deposit
 

requirements

 
frightening

stipulated

 
encountered
 

Government

 
grounds
 
cleared
 

physically

 
effect
 

tendency

 

attempt

 
prohibit

bidding

 

favored

 

extension

 

clause

 

Monday

 

embodied

 
decision
 

prohibitive

 

render

 

wreckage