FREE BOOKS

Author's List




PREV.   NEXT  
|<   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  
rely filled with neat cement grout. _Box Drains._--Various methods of forming the box drains were considered, such as using half-tile drains, or a metal form, or a collapsible form which could be withdrawn, but it was finally decided to build boxes in which the side toward the rock was open and the joints in the boxes and against the rock were plastered with cement mortar. These boxes were left in place. Fig. 1, Plate LI, shows the tie-rods and box drains in place, and holes being cut near the bottom of the drains for the pipes leading through the wall. _Forms._--Fig. 1, Plate LI, shows the form used on the south side of the work. The materials were of good quality, and the form, which was about 50 ft. long, was used to build twelve sections, or about 600 ft. of wall. The form was tied in at the top and bottom by cables attached to rods drilled into the rock, and it was thought that, with the trusses to stiffen the middle section of the form, it would not be necessary to use raker braces against it. This would have been desirable, as the placing of the raker braces took considerable time. It was found, however, that the form was not sufficiently rigid, as it bulged at the middle section and could not be held by the trusses. Two or three sets of raker braces, about 12 ft. apart, were used, and in addition, rods with turnbuckles were placed through the form and fastened to the tie-rods, and thus the form was held in place successfully. On the forms built later, the trusses were omitted, and raker braces, about every 6 ft., were used. The rods which screwed into the turnbuckles were removed before the form was moved. The photograph, Fig. 4, Plate LII, was taken inside the concrete form for the lower face wall on the north side, and shows the drains leading through the wall, the turnbuckles attached to the tie-rods, the cables attached to rods in the rock, and the braces to keep the form from coming in; these braces, of course, were removed as the concrete came up. The form was built low and wedged up into position. After a section of concrete had set sufficiently, the wedges were knocked out, the form was lowered and moved from the wall, and was then moved along the lowest waling piece by block and tackle to its new position. Fig. 4, Plate L, shows the forms used on the north side of the work. A section, 1 ft. square, at the top of the bridge seat of the lower face wall, was left out, so that the bottom of the form f
PREV.   NEXT  
|<   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:

braces

 

drains

 

section

 

concrete

 

turnbuckles

 

bottom

 

trusses

 

attached

 

middle

 
leading

removed
 

cement

 

position

 
cables
 

sufficiently

 

inside

 
fastened
 

addition

 
successfully
 

filled


screwed
 

omitted

 

photograph

 

tackle

 

waling

 

bridge

 

square

 

lowest

 

wedged

 

coming


lowered

 

knocked

 

wedges

 
materials
 

quality

 

twelve

 

sections

 
collapsible
 

decided

 
mortar

plastered
 
joints
 

finally

 

withdrawn

 

considerable

 

placing

 

desirable

 

bulged

 
thought
 

methods