FREE BOOKS

Author's List




PREV.   NEXT  
|<   382   383   384   385   386   387   388   389   390   391   392   393   394   395   396   397   398   399   400   401   402   403   404   405   406  
407   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429   430   431   >>   >|  
rk over the contract price, and the amount of such increased cost caused by the delay and action of the Government as aforesaid, and the amount already paid the contractor over and above the contract price." Under this act Commodore J.A. Marchand, Chief Engineer J.W. King, and Paymaster Edward Foster, of the Navy, were designated by the Secretary of the Navy to make the investigation required. These officers on the 26th day of November, 1867, made a report of their proceedings, which was submitted to the Senate with a tabulated statement of all the claims examined by them and their findings thereon. It appears by this report that the claims of the beneficiaries mentioned in the bill herewith returned were examined by the board, and that nothing was found due thereon under the terms of the law directing their examination. These claims have frequently been before Congress since that time. They have been favorably reported and acted upon a number of times, and have also been more than once strongly condemned by committees to whom they were referred. A resolution was passed in 1871 by the Congress referring these and other claims of a like character to the Court of Claims for adjudication, but it was vetoed by the President for reasons not necessarily affecting the merits of the claims. The case of Chouteau _vs_. The United States, reported in Fifth Otto, page 61, which arose out of the contract to build a vessel called the _Etlah_, appears to present the same features that belong to the claims here considered. It is stated in the report of the House committee on this bill that "the _Squando_ and _Nauset_ were identical in the original plans and the changes and alterations thereon with the _Etlah_ and _Shiloh_, built in St. Louis;" and yet the Supreme Court of the United States distinctly decided in the _Etlah_ case that the only pretext for further compensation should be sought for in the contract, where the contractor had evidently been content to provide for all the remedy he desired. It seems, then, that the contractors mentioned in this bill, after entering into contracts plainly indicating that changes of plans and consequent delay in their work were in their contemplation, availed themselves of the remedy which they themselves had provided, and thereupon received about 50 per cent in the case of two of these vessels of the contract price for extra work, giving the Government a receipt in full. When soon
PREV.   NEXT  
|<   382   383   384   385   386   387   388   389   390   391   392   393   394   395   396   397   398   399   400   401   402   403   404   405   406  
407   408   409   410   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429   430   431   >>   >|  



Top keywords:

claims

 

contract

 
report
 

thereon

 

United

 

Congress

 
remedy
 
States
 

mentioned

 

appears


reported
 
examined
 
contractor
 

Government

 

amount

 

stated

 
features
 

belong

 

committee

 

considered


merits

 

vessels

 

original

 

Nauset

 

identical

 

Squando

 

Chouteau

 

giving

 

receipt

 

present


called

 

vessel

 

consequent

 

indicating

 

content

 
evidently
 
contemplation
 

affecting

 

sought

 

plainly


contracts
 
entering
 

desired

 

provide

 

availed

 

Supreme

 
distinctly
 

decided

 
Shiloh
 

contractors