,160.86| 2.818 |
| | | | |
Material: | | | | |
Lumber | | 487.77| | |
Hardware | | 202.79| 690.56| | 1.676
| | | | |
Concreting: | | | | |
Labor | 0.50 | 142.00| | |
" | 0.344 | 11.00| | |
" | 0.281 | 947.81| 1,100.81| 2.672 |
Material: | | | | |
Rock | | 317.30| | |
Sand | | 385.72| | |
Cement | |1,581.97| | |
Motor and Hoist: | | | | |
Rental | | 406.56| | |
Power | | 83.53| 2,735.08| | 6.638
| | | | |
Plastering | | | | |
(3,000 sq. ft.): | | | | |
Labor, Plasterers | 0.75 | 116.50| | |
Labor | 0.46-7/8| 15.00| | |
" | 0.37-1/2| 198.52| | |
" | 0.281 | 105.66| 435.68| 14.52 |
| | | | per sq. ft. |
Material: | | | | |
Sand | | 8.64| | |
Cement | | 66.10| | |
Alum and Potash | | 16.00| 90.74| 3.25 |
| | | | per sq. ft. |
| | | | |
Cement Wash | | | | |
(8,560 sq. ft.): | | | | |
Labor | 0.48-3/4| 50.00| | |
" | 0.281 | 47.68| 97.68|1.14 per |
| | | | 100 sq ft. |
Material:
|