FREE BOOKS

Author's List




PREV.   NEXT  
|<   270   271   272   273   274   275   276   277   278   279   280   281   282   283   284   285   286   287   288   289   290   291   292   293   294  
295   296   297   298   299   300   301   302   303   304   305   306   307   308   309   310   311   312   313   314   315   316   317   318   319   >>   >|  
of the wall were then replaced by an open viaduct, with the piers placed edgeways to the sea, the openings between them being spanned by ten cast-iron girders each 42 feet long. This accident induced the engineer to alter the contour of the sea wall, so that it should present a diminished resistance to the force of the waves. But the sea repeated its assaults, and made further havoc with the work; entailing heavy expenses and a complete reorganisation of the contract. Increased solidity was then given to the masonry, and the face of the wall underwent further change. At some points outworks were constructed, and piles were driven into the beach about 15 feet from the base of the wall, for the purpose of protecting its foundations and breaking the force of the waves. The work was at length finished after about three years' anxious labour; but Mr. Stephenson confessed that if a long tunnel had been made in the first instance through the solid rock of Penmaen Mawr, a saving of from 25,000 to 30,000 pounds would have been effected. He also said he had arrived at the conclusion that in railway works engineers should endeavour as far as possible to avoid the necessity of contending with the sea; {324} but if he were ever again compelled to go within its reach, he would adopt, instead of retaining walls, an open viaduct, placing all the piers edgeways to the force of the sea, and allowing the waves to break upon a natural slope of beach. He was ready enough to admit the errors he had committed in the original design of this work; but he said he had always gained more information from studying the causes of failures and endeavouring to surmount them than he had done from easily-won successes. Whilst many of the latter had been forgotten, the former were indelibly fixed in his memory. But by far the greatest difficulty which Robert Stephenson had to encounter in executing this railway, was in carrying it across the Straits of Menai and the estuary of the Conway, where, like his predecessor Telford when forming his high road through North Wales, he was under the necessity of resorting to new and altogether untried methods of bridge construction. At Menai the waters of the Irish Sea are perpetually vibrating along the precipitous shores of the strait; rising and falling from 20 to 25 feet at each successive tide; the width and depth of the channel being such as to render it available for navigation by the largest ships.
PREV.   NEXT  
|<   270   271   272   273   274   275   276   277   278   279   280   281   282   283   284   285   286   287   288   289   290   291   292   293   294  
295   296   297   298   299   300   301   302   303   304   305   306   307   308   309   310   311   312   313   314   315   316   317   318   319   >>   >|  



Top keywords:

railway

 

edgeways

 

viaduct

 

necessity

 
Stephenson
 

Whilst

 

successes

 

forgotten

 
indelibly
 

failures


natural
 
gained
 

design

 

errors

 

committed

 

original

 

memory

 

surmount

 

allowing

 

endeavouring


information
 

studying

 

easily

 

Telford

 

precipitous

 

shores

 
strait
 
rising
 

vibrating

 
perpetually

waters

 

construction

 
falling
 

render

 

navigation

 
largest
 
channel
 

successive

 

bridge

 

methods


estuary

 

Straits

 

Conway

 
carrying
 

difficulty

 
Robert
 

encounter

 

executing

 

predecessor

 
placing