FREE BOOKS

Author's List




PREV.   NEXT  
|<   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42  
43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   >>   >|  
he pipes probably occurred at the crossing of the puddle trench. A fissure in the puddle was created, affording a creep for the water, which, once set up, would rapidly increase the breach by scour; and this event was favored by the manner in which the bank had been constructed and the unsuitability of the material used, which, in the words of one engineer, had more the appearance of a quarry tip than of a bank intended to store water. This opinion of the cause of failure was, however, not adopted universally by engineers, the line of pipes when examined being found to be, although disjointed, fairly in line; and there having occurred a land slip in the immediate neighborhood, it was suggested that the rupture might be caused by a slip also having taken place here, especially as the substratum was of flagstone rock tilted at a considerable angle. The formation was millstone grit. This catastrophe induced an examination to be made of other storage reservoir dams in the same district, and a report on the subject was presented to Parliament by Sir Robert Rawlinson. [Illustration: TYPICAL MASONRY AND EARTHWORK DAMS OF THE WORLD.] The dam of Stubden reservoir, of the Bradford water supply, also on the millstone grit, was constructed about 1859, and caused considerable anxiety for a length of time, as leakage occurred in the culvert carrying the pipes, under the embankment at a point a short distance on the down stream side of the puddle trench. This was repaired to some extent by lining with cast iron plates; and an entirely independent outlet was made by driving a curved tunnel into the hill side clear of the ends of the dam and lining it with cast iron plates. In this tunnel was then laid the main of 2 ft. diameter, and as the original culvert again became leaky, the water had to be lowered, the old masonry pulled out, and the space filled in with puddle. The Leeming compensation reservoir of the same water supply, with a dam of 50 ft. in height, and culvert outlet, had to be treated somewhat in the same manner, as, although the reservoir had never been filled with water, in 1875, when it was examined previous to filling, it was found that the culvert was cracked in all directions; and it was deemed best to fill it up with Portland cement concrete, and drive a tunnel outlet through the hill side, as described in the case of the Stubden reservoir. The Leeshaw dam, which was being constructed at that time upon the same
PREV.   NEXT  
|<   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42  
43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   >>   >|  



Top keywords:

reservoir

 

puddle

 

culvert

 

outlet

 

occurred

 

constructed

 
tunnel
 

supply

 

examined

 
Stubden

plates

 

considerable

 

caused

 

millstone

 
lining
 

filled

 
trench
 

manner

 

cement

 

repaired


concrete
 

directions

 

deemed

 

Portland

 

extent

 
stream
 

anxiety

 

length

 

Bradford

 

Leeshaw


leakage

 

carrying

 

distance

 

embankment

 

Leeming

 
compensation
 

pulled

 
masonry
 

lowered

 

diameter


original

 
height
 

driving

 

curved

 

previous

 

filling

 
independent
 

treated

 
cracked
 
examination