FREE BOOKS

Author's List




PREV.   NEXT  
|<   78   79   80   81   82   83   84   85   86   87   88   89   90   91   92   93   94   95   96   97   98   99   100   101   102  
103   104   105   106   107   108   109   >>  
ed. The surface is divided into sections by earthen dikes and the space inside the dikes filled with water to a depth of two or three inches. The water covering is maintained for two weeks or longer. No traffic is permitted on the surface for one month, and in cold weather traffic may be kept off the surface for a longer period. =Expansion Joints.=--To permit the concrete slab to accommodate itself to changes in dimension due to temperature changes, expansion joints 1/2 inch wide are placed about every thirty feet. These consist of a sheet of some prepared bituminous material placed in position as the concrete is poured. Experience seems to indicate that in spite of the expansion joints, the concrete will crack more or less and many engineers think it advisable to omit expansion joints in constructing the pavement and when cracks develop to pour bituminous material into them, thus forming expansion joints. The prevailing practice in rural highway construction is to omit the expansion joints, but they are commonly adopted in city pavements. =Reinforcing.=--To minimize the cracking, either bar or wire mesh reinforcing is used in the concrete. If bars are used they are placed in the concrete as it is poured so as to form a belt around each section about 15 feet square. If the mesh type is employed, a part of the layer of concrete is placed and smoothed off and a strip of the mesh laid in place. Additional concrete is then poured on top of the mesh to bring the slab to the required thickness. =Bituminous Coatings on Concrete Surfaces.=--The concrete road surface is sometimes coated with a layer of bituminous material and stone chips or gravel pebbles. This is particularly advisable where no really satisfactory aggregates are available and the concrete surface would not possess sufficient durability. The bituminous material is applied hot to the surface and is then covered with stone chips or gravel pebbles, ranging in size from 3/4 inch down to 1/4 inch, the resulting coating being about 3/4 inch thick. Many failures of this type of surface have been recorded due to the difficulty of securing adhesion to the concrete. This seems to be due in part to inability to get the proper bituminous materials and in part to climatic effects. Considerable progress has been made in developing this type of surface and it may eventually become a satisfactory maintenance method. =Characteristics.=--The concrete road is of a g
PREV.   NEXT  
|<   78   79   80   81   82   83   84   85   86   87   88   89   90   91   92   93   94   95   96   97   98   99   100   101   102  
103   104   105   106   107   108   109   >>  



Top keywords:

concrete

 

surface

 

expansion

 
bituminous
 
joints
 

material

 
poured
 

pebbles

 

advisable

 

satisfactory


gravel
 

longer

 

traffic

 

employed

 

square

 
section
 

Coatings

 

Bituminous

 

thickness

 
required

aggregates

 
Concrete
 

Surfaces

 

Additional

 

coated

 

smoothed

 

ranging

 
maintenance
 

adhesion

 

inability


securing

 

difficulty

 

failures

 

recorded

 

proper

 

materials

 

eventually

 

developing

 

progress

 

climatic


effects

 

Considerable

 

method

 

applied

 

covered

 

durability

 
sufficient
 

possess

 

coating

 

Characteristics