after the contracts are let and the work
begun is both expensive and foolish. If you find it difficult to
visualize an actual house from the drawings, a model made from wall
board or similar material is a wise precaution. Fashioned on the same
scale of one quarter of an inch to the foot, it is your proposed house
in the little, and on seeing it no doubts are left. Windows and doors
are all in their proper places. The exterior is painted to match the
color and simulate the material that is to be used. Finally, the model
can be taken apart so that you can study the interior of bedroom and
living room floors. Such models, of course, are not included in the
architect's fee but the cost of one for an average house is under
$100. If you can visualize your proposed home thoroughly by it, the
expense is well warranted.
The architect can be of great service in the matter of contractor's
bids. He knows the past performances of those operating in the
vicinity where you propose building and can suggest the men or firms
whose work is most satisfactory. From four to eight general
contractors, that is, individuals or firms competent to undertake the
complete building operation, ought to be invited to submit sealed
bids. Each is supplied with a complete set of plans and specifications
by the architect and given from ten days to two weeks in which to
submit their bids. In addition to the total price for the work, these
bids, by common custom, give the names of the chief sub-contractors
such as plumber, electrician and the like, with the amount of money
allocated for the work of each.
On a set day, usually a Saturday afternoon, owner and architect meet,
open the bids, and compare the offers made by the various contractors.
Most of them include alternate provisions on condition that they be
allowed to substitute materials or methods of construction not
according to the specifications. The contractor who submits the lowest
bid would logically be the one selected but here again the architect's
judgment is valuable. First, he can rapidly determine whether the
provisional saving suggested by substitution of unspecified materials
is a wise change. Second, he knows whether the bidder under
consideration is dependable or inclined to skimp in hidden but
essential points.
There is, also, the possible chance that none of the bids submitted
come within the sum the owner is prepared to spend. Then comes the
task of revising plans and specific
|