FREE BOOKS

Author's List




PREV.   NEXT  
|<   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44  
>>  
tions, but if such work shall prove upon inspection to have been well done the contractor may make a charge of the amount which would have been allowed for that part of the work had it passed inspection. When the work is completed it must pass the final inspection of the supervisor, or such person as the Secretary of the Interior may designate for the purpose. 1. CLEARING OUT THE DEBRIS The debris now filling up the interior is to be removed down to the floor level, or the original ground level. The debris covering an area measuring 10 feet from the exterior walls of the building in every direction is also to be removed. This work is to be carried on in conjunction with the underpinning of the walls, and is to be dependent upon the progress of the latter, the work being done as required by the person holding the contract for the underpinning. All proper precautions must be observed during the progress of the work to prevent any injury to the building, the walls being properly braced and supported before excavation is commenced. The contractor will be held responsible for any injury to the building. Any objects found of archeologic or other value properly belong to the United States and must be deposited in the National Museum. The material removed from the building and from the area about it is to be removed to a proper distance, not less than 100 yards from the building. Proper drainage channels must be provided to keep the excavated area permanently clear of water. 2. UNDERPINNING WALLS The walls where eroded at the ground level are to be underpinned with hard-burned brick, laid in good cement mortar and extending to a depth of at least 12 inches below the original ground level. This work must be carried on gradually and very carefully in conjunction with the clearing out of the debris. The under surfaces of the overhanging walls must be carefully trimmed to afford solid horizontal bearings against the brickwork. The face of the brickwork is to be set back at least 1 inch and not more than 2 inches from the face of the wall, and the brickwork is to be plastered with a coating of cement mortar, 1 to 2 inches thick, bringing it out flush with the outer wall. 3. FILLING IN OPENINGS The broken-out lintels of openings are to be replaced by wooden lintels composed of squared lumber, 2 by 4 inches in size, laid side by side across nearly the whole thickness of the walls, with not more than 1 inch space betwee
PREV.   NEXT  
|<   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44  
>>  



Top keywords:

building

 
removed
 

inches

 
brickwork
 

debris

 

ground

 
inspection
 

conjunction

 

underpinning

 

original


contractor

 
progress
 

carefully

 

cement

 

mortar

 

properly

 

injury

 
proper
 

carried

 

person


lintels

 

burned

 

underpinned

 

replaced

 

extending

 
FILLING
 
OPENINGS
 

openings

 
channels
 

provided


drainage
 

betwee

 

Proper

 

excavated

 
UNDERPINNING
 

thickness

 

permanently

 

eroded

 
overhanging
 

trimmed


surfaces

 
afford
 

lumber

 

horizontal

 

bearings

 
squared
 

composed

 
gradually
 

bringing

 

plastered