FREE BOOKS

Author's List




PREV.   NEXT  
|<   167   168   169   170   171   172   173   174   175   176   177   178   179   180   181   182   183   184   185   186   187   188   189   190   191  
192   193   194   195   196   197   198   199   200   201   202   203   204   205   206   207   208   209   210   211   212   213   214   215   216   >>   >|  
re we read the names "Lake Timsah," "The Bitter Lakes" and others. They were found to be thickly incrusted with salt on the bottom and sides, indicating that at one time they had been filled with sea-water; it is indeed must probable that the whole isthmus was at a very remote period entirely submerged. In the construction of the canal these depressions were made to play a very important part. The line of the canal was carried directly through them; the shallower were brought to a sufficient depth by dredging; the deeper were simply filled with water and required nothing more for safe navigation than an indication of the channel by buoys. Thus, in the whole length of the canal, reckoned at 88 geographical miles, there are 66 miles of actual digging; 14 miles of dredging through the lakes; and 8 miles, where neither digging nor dredging was required. Water began to flow from the Mediterranean into the canal in February, 1869, and from the Red Sea in July of the same year; and by October, the lakes, and the canal in its whole length, were filled with water navigable by vessels of the highest class. The water-way thus obtained has a width at the surface varying from 197 feet at deep cuttings, to 225 feet at lower ground. The sides slope to a width at the bottom of 72 feet, and an average depth of 26 feet is secured along the whole course. As the water is at one level from sea to sea, the canal is without obstruction of any kind. No locks, dams, or water-gates are required, and vessels enter the canal from either end and pursue their journey without interruption or detention. So great, however, was the eagerness of trade to take advantage of the new route, that the volume of traffic increased within a very short time after the opening of the canal to such an extent as to cause serious delays in the transit, and a number of schemes were brought forward for building other canals by which the two seas might be united. In the end, all these plans were abandoned, and it was decided to widen the canal sufficiently to enable it to meet the increased demand upon its carrying capacity. It may not be without interest to note the growth of traffic in the canal by a few figures. From 486 ships which passed through in 1870, the number rose to 3,100 in 1886; while the receipts increased from $1,031,875 in 1870, to $11,541,090 in 1886. The canal, when completed, was found to have cost twenty million pounds sterling, a sum far in adv
PREV.   NEXT  
|<   167   168   169   170   171   172   173   174   175   176   177   178   179   180   181   182   183   184   185   186   187   188   189   190   191  
192   193   194   195   196   197   198   199   200   201   202   203   204   205   206   207   208   209   210   211   212   213   214   215   216   >>   >|  



Top keywords:

filled

 

increased

 
required
 

dredging

 

brought

 

vessels

 

digging

 

length

 

number

 

traffic


bottom

 

delays

 

forward

 

interruption

 

detention

 

building

 
journey
 

schemes

 

transit

 

volume


advantage

 

eagerness

 

pursue

 

opening

 
extent
 

receipts

 

passed

 
sterling
 

pounds

 
million

twenty
 
completed
 

decided

 

abandoned

 

sufficiently

 

enable

 

united

 
demand
 
interest
 

growth


figures

 
obstruction
 
carrying
 

capacity

 

canals

 

important

 
carried
 

directly

 

submerged

 

construction