FREE BOOKS

Author's List




PREV.   NEXT  
|<   79   80   81   82   83   84   85   86   87   88   89   90   91   92   93   94   95   96   97   98   99   100   101   102   103  
104   105   106   107   108   109   110   111   112   113   >>  
-five feet, but its greatest breadth, as seen at low-water of spring-tides, is only twenty-three feet; hence it was not possible to obtain a base for a building of greater diameter than eighteen feet. The surface of the rock was also so rugged that it was necessary to excavate part of the foundation-pit of the building to the depth of seven feet. The difficulties were still further increased on account of the foundation being partly under the level of the lowest tides, so that a coffer-dam was required. It was further necessary, after each tide's work, to remove and carry ashore part of this coffer-dam; so that on the return of the workmen at ebb-tide much time was lost in readjusting the coffer-dam, and in pumping the water out of the foundation-pit. Some idea may be formed of the difficulties attending the early stages of this work, from the fact that during the whole of the first season, or summer of 1813, the workmen could not command more than forty-one hours' work upon the rock; during the second season the time was only fifty-three hours. These two years were entirely occupied in excavating and preparing the foundation, and in laying ten stones, or the half course of masonry, which brought the foundation to a uniform level for the first entire course of the building. Mr. Stevenson contrasts this slow progress with that made at the Bell Rock during the first two seasons. Although this building was situated twelve miles from the shore, three courses were erected, the diameter of the base being forty-two feet, besides the erection of a beacon-house or barrack for the workmen. 'The establishment for the works at the Bell Rock was of course on a much larger scale than that of the Carr Rock; but still the latter was equally effective, and the same apparatus, artificers, and seamen, were employed at both.' During the third year's work, the second course of the masonry was completed upon the Carr; and nine stones of the third course were laid by the 3rd of October, when a heavy ground-swell obliged the workmen precipitately to leave the rock and take to their boats. Before the cement was fixed, the surge of the sea had washed it out; the oaken trenails were wrenched off, and the whole of the nine blocks of stone swept off the rock and lost in deep water, though they had been completely dove-tailed and fitted on the same principles as the masonry of the Bell-Rock lighthouse, where not a single stone was lost during th
PREV.   NEXT  
|<   79   80   81   82   83   84   85   86   87   88   89   90   91   92   93   94   95   96   97   98   99   100   101   102   103  
104   105   106   107   108   109   110   111   112   113   >>  



Top keywords:
foundation
 
workmen
 
building
 
masonry
 
coffer
 
stones
 

season

 

difficulties

 

diameter

 
artificers

apparatus
 

seamen

 

larger

 
effective
 

principles

 

tailed

 
equally
 

fitted

 
lighthouse
 

courses


erected

 

twelve

 

Although

 

situated

 

erection

 

barrack

 
employed
 

establishment

 

single

 

beacon


trenails

 

precipitately

 

obliged

 
seasons
 

washed

 

cement

 
Before
 
wrenched
 

blocks

 
completed

During
 

completely

 

ground

 

October

 

lowest

 

required

 

partly

 

account

 
increased
 

return