FREE BOOKS

Author's List




PREV.   NEXT  
|<   484   485   486   487   488   489   490   491   492   493   494   495   496   497   498   499   500   501   502   503   504   505   506   507   508  
509   510   511   512   513   514   515   516   517   518   519   520   521   522   523   524   525   526   527   528   529   530   531   532   533   >>   >|  
ich he had performed and materials furnished. It is only alleged that the glass tiling and frames actually put in the building were slightly thicker than those required by the contract, and this alleged increased thickness seems to be fairly represented in a general way by the claim that some of the glass and frames which were required to be 1 inch thick were actually put in 1 inch and a quarter thick. Upon this statement it must be admitted that the sum above stated as the value of this extra thickness is somewhat startling. In the language of the report upon this bill by the Supervising Architect, "a claim of $47,159.02 for such slight excess on work the price of which was $35,217.57 is hardly entitled to consideration." The claim, as well as the award of the experts last named, reach their astonishing proportions by the application of weights to the question in the following manner: A certain area is measured. A square foot of the tiling actually put in is weighed, and a square foot of the tiling required by the contract is also weighed. Both these weights are multiplied by the area. The lesser aggregate weight is deducted from the greater, and the difference is divided by the weight of a square foot of the lightest tiling, thus reducing it to square feet of such lightest tile. These square feet are multiplied by the price agreed to be paid by the contract for each superficial foot, and an item of extra work is determined. Thus additional weight in constructed and finished tiling is converted, as far as price and measurement are concerned, into finished tile, which more than doubles the quantity actually laid down. This can not be right. And yet the bill herewith returned directs the Secretary of the Treasury to settle this claim for extra work upon the basis of the report of the experts who have adopted this mode of adjustment; or, if not satisfied with their report, he shall within thirty days from the passage of the act cause a reweighing of said material to be made by two sworn experts, one to be appointed by him and one by the claimant, and a third to be appointed by these two in case they can not agree. The bill further provides that he shall then pay to said Willbur the difference of excess in weight and superficial measurement as found by said experts between the illuminated tiling and frames furnished and that contracted for at the contract prices for such work and material. There are features of
PREV.   NEXT  
|<   484   485   486   487   488   489   490   491   492   493   494   495   496   497   498   499   500   501   502   503   504   505   506   507   508  
509   510   511   512   513   514   515   516   517   518   519   520   521   522   523   524   525   526   527   528   529   530   531   532   533   >>   >|  



Top keywords:

tiling

 

square

 

experts

 

weight

 

contract

 

frames

 
report
 
required
 

appointed

 

lightest


excess

 
measurement
 

multiplied

 

weighed

 
superficial
 

material

 

finished

 
difference
 

weights

 

furnished


thickness

 

alleged

 

returned

 
directs
 

Secretary

 
herewith
 

Treasury

 

settle

 

contracted

 

adopted


concerned

 

features

 

building

 

converted

 

doubles

 

prices

 

quantity

 

illuminated

 

adjustment

 

claimant


performed
 

materials

 

constructed

 

satisfied

 

thirty

 

reweighing

 

passage

 

Willbur

 

entitled

 

consideration